Energy Projects Near You

Solar, wind and battery projects near Windermere (LA23)

6 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of LA23 (Westmorland and Furness): 2 approved but not yet running, 3 operational. The largest live scheme is North James Cropper, Garnett Bridge Road (3 MW solar farm, approved on 17 January 2024, not yet built), 10.0 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6projects within 10 km
0awaiting a decision
2approved, not running
3operational

Projects within 10 km of LA23

Projects of 1 MW and more (3)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
North James Cropper, Garnett Bridge Roadsolar farmsolar farm3approved, not builtupdated Feb 2024Jan 2023granted Jan 2024Feb 2024Westmorland and Furness10.0
James Cropper Effluent Plantsolar farmsolar farm1application withdrawnupdated Jun 2020Dec 2019—Jun 2020Westmorland and Furness10.0
Burneside Mill, Burnesiderooftop solarrooftop solar1operationalupdated Jan 2022Feb 2021granted Apr 2021Jan 2022Westmorland and Furness10.0
Smaller schemes under 1 MW, mostly rooftop solar (3)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Low Wood Hotelrooftop solarrooftop solar0.2approved, not built may be out of dateupdated Mar 2023Dec 2022granted Mar 2023Mar 2023Westmorland and Furness4.9
Burneside Millrooftop solarrooftop solar0.5operationalupdated Dec 2019——Dec 2019Westmorland and Furness9.9
Burneside Mill Solar Array - Phase 3rooftop solarrooftop solar0.3operationalupdated Apr 2021Apr 2021granted Apr 2021Apr 2021Westmorland and Furness10.0

Distance from the average position of the LA23 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm201003
Rooftop solar401300.2

MW in pipeline: pending, approved and under-construction capacity.

How Westmorland and Furness decides solar, wind and battery applications

ApplicationsWestmorland and FurnessUK
Decided applications (solar, wind, battery)6810,236
Refused30 (44%)19%
Solar refused14 of 4212%
Onshore wind refused14 of 1945%
Battery storage refused2 of 716%
Median time from submission to decision34.6 weeks17.0 weeks
Appeals lodged / allowed9 / 9—

All projects in Westmorland and Furness

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near LA23, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.