Energy Projects Near You

Solar, wind and battery projects near Kendal (LA9)

16 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of LA9 (Westmorland and Furness): 1 is waiting for a planning decision, 3 approved but not yet running, 7 operational. The largest live scheme is Eskrigg End Road, Old Hutton (200 MW battery storage, approved on 10 July 2025, not yet built), 6.2 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

16projects within 10 km
1awaiting a decision
3approved, not running
7operational

Projects within 10 km of LA9

Projects of 1 MW and more (11)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
North James Cropper, Garnett Bridge Roadsolar farmsolar farm3approved, not builtupdated Feb 2024Jan 2023granted Jan 2024Feb 2024Westmorland and Furness3.6
James Cropper Effluent Plantsolar farmsolar farm1application withdrawnupdated Jun 2020Dec 2019—Jun 2020Westmorland and Furness3.6
Burneside Mill, Burnesiderooftop solarrooftop solar1operationalupdated Jan 2022Feb 2021granted Apr 2021Jan 2022Westmorland and Furness3.6
Greenmoor Bankbattery storagebattery storage50refusedupdated Nov 2018May 2017refused Jan 2018Nov 2018Westmorland and Furness5.5
Greaves Solar Farmsolar farmsolar farm5operationalupdated Jun 2016Aug 2015granted Nov 2015Jun 2016Westmorland and Furness5.8
Eskrigg End Road, Old Huttonbattery storagebattery storage200approved, not builtupdated Jul 2025Oct 2024granted Jul 2025Jul 2025Westmorland and Furness6.2
Lambrigg Wind Farmwind farmwind farm6.5operationalupdated Apr 2011Jun 1998granted Jul 1999Apr 2011Westmorland and Furness7.1
Killington Wind Farmwind farmwind farm10.2abandonedupdated Dec 2014Oct 2012granted Feb 2014Dec 2014Westmorland and Furness7.6
Armistead Wind Farmwind farmwind farm12operationalupdated May 2013Mar 2008granted Jul 2010May 2013Westmorland and Furness8.7
Firbank Wind Farmwind farmwind farm9.7refusedupdated Oct 2011Sep 1998refused Dec 1998Oct 2011Westmorland and Furness9.2
Barkin House Wind Farmwind farmwind farm4.7refusedupdated Oct 2011Sep 1998refused Apr 1999Oct 2011Westmorland and Furness9.2
Smaller schemes under 1 MW, mostly rooftop solar (5)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Kendal Leisure Centre, Burton Roadrooftop solarrooftop solar0.2application submittedJun 2026——Westmorland and Furness1.2
Murley Moss - Additional Solar Design And Buildsolar farmsolar farm—under constructionupdated Mar 2026——Mar 2026Westmorland and Furness1.7
South Stilling Tanks Solar Farmsolar farmsolar farm0.5operationalupdated Jul 2023Sep 2020granted Apr 2021Jul 2023Westmorland and Furness3.2
Burneside Mill Solar Array - Phase 3rooftop solarrooftop solar0.3operationalupdated Apr 2021Apr 2021granted Apr 2021Apr 2021Westmorland and Furness3.6
Burneside Millrooftop solarrooftop solar0.5operationalupdated Dec 2019——Dec 2019Westmorland and Furness3.7

Distance from the average position of the LA9 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm502203
Rooftop solar410300.2
Wind farm500220
Battery storage20101200

MW in pipeline: pending, approved and under-construction capacity.

How Westmorland and Furness decides solar, wind and battery applications

ApplicationsWestmorland and FurnessUK
Decided applications (solar, wind, battery)6810,236
Refused30 (44%)19%
Solar refused14 of 4212%
Onshore wind refused14 of 1945%
Battery storage refused2 of 716%
Median time from submission to decision34.6 weeks17.0 weeks
Appeals lodged / allowed9 / 9—

All projects in Westmorland and Furness

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.