Energy Projects Near You

Killington Wind Farm (10.2 MW)

Killington Wind Farm is a 10.2 MW wind farm project in Westmorland and Furness, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: abandoned; the record was last updated on 30 December 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10.2 MWwind farm
abandonedstatus in REPD
30 December 2014record last updated
Westmorland and Furnesscouncil area

Planning timeline

DateStage
1 October 2012Application submitted
11 February 2014Planning permission granted
1 March 2014Secretary of State intervened

Project details

Technology
wind farm
Capacity
10.2 MW
Status (REPD)
abandoned
Record last updated
30 December 2014
Operator or applicant
Banks Renewables
Planning authority
Westmorland and Furness
Planning application reference
SL/2012/0845
Turbines
3
Address (REPD)
Near M6 near Killington, Cumbria
Council area (by location)
Westmorland and Furness
Time to decision
71 weeks
REPD reference
4090

Who decides

ApplicationsWestmorland and FurnessUK
Decided applications (solar, wind, battery)6810,236
Refused30 (44%)19%
Solar refused14 of 4212%
Onshore wind refused14 of 1945%
Battery storage refused2 of 716%
Median time from submission to decision34.6 weeks17.0 weeks
Appeals lodged / allowed9 / 9—

Other large projects within 10 km

ProjectTypeMWStatuskm
Lambrigg Wind Farmwind farm6.5operational1.5
Firbank Wind Farmwind farm9.7refused2.3
Greenmoor Bankbattery storage50refused4.0
Eskrigg End Road, Old Huttonbattery storage200approved, not built4.0
Armistead Wind Farmwind farm12operational5.4
Greaves Solar Farmsolar farm5operational5.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.3241, -2.6258).