Energy Projects Near You

Greenmoor Bank (50 MW battery storage)

Greenmoor Bank is a 50 MW battery storage project in Westmorland and Furness, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 5 January 2018; the record was last updated on 23 November 2018.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

50 MWbattery storage
refusedstatus in REPD
23 November 2018record last updated
Westmorland and Furnesscouncil area

Planning timeline

DateStage
9 May 2017Application submitted
5 January 2018Refused by the planning authority

Project details

Technology
battery storage (stand-alone storage)
Capacity
50 MW
Status (REPD)
refused
Record last updated
23 November 2018
Operator or applicant
Greenmore Bank Storage
Planning authority
Westmorland and Furness
Planning application reference
SL/2017/0425
Address (REPD)
Land to the north of Old Hutton Substation, Greenmoor Bank Old Hutton KENDAL
Council area (by location)
Westmorland and Furness
Time to decision
34 weeks
REPD reference
6957

Who decides

ApplicationsWestmorland and FurnessUK
Decided applications (solar, wind, battery)6810,236
Refused30 (44%)19%
Solar refused14 of 4212%
Onshore wind refused14 of 1945%
Battery storage refused2 of 716%
Median time from submission to decision34.6 weeks17.0 weeks
Appeals lodged / allowed9 / 9—

Other large projects within 10 km

ProjectTypeMWStatuskm
Eskrigg End Road, Old Huttonbattery storage200approved, not built0.7
Greaves Solar Farmsolar farm5operational1.8
Armistead Wind Farmwind farm12operational3.4
Killington Wind Farmwind farm10.2abandoned4.0
Lambrigg Wind Farmwind farm6.5operational4.7
Firbank Wind Farmwind farm9.7refused6.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.2999, -2.6706).