Eskrigg End Road, Old Hutton (200 MW battery storage)

Eskrigg End Road, Old Hutton is a 200 MW battery storage project in Westmorland and Furness, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 10 July 2025, not yet built; the record was last updated on 28 July 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

200 MWbattery storage
approved, not builtstatus in REPD
28 July 2025record last updated
Westmorland and Furnesscouncil area

Planning timeline

DateStage
4 October 2024Application submitted
10 July 2025Planning permission granted
10 July 2030Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
200 MW
Status (REPD)
approved, not built
Record last updated
28 July 2025
Operator or applicant
Harmony MS Limited
Planning authority
Westmorland and Furness
Planning application reference
2024/2413/FPA
Address (REPD)
South of Eskrigg End Road Old Hutton
Council area (by location)
Westmorland and Furness
Time to decision
40 weeks
Name in REPD
Eskrigg End Road, Old Hutton - Battery Energy Storage System
REPD reference
17376

Who decides

ApplicationsWestmorland and FurnessUK
Decided applications (solar, wind, battery)6810,236
Refused30 (44%)19%
Solar refused14 of 4212%
Onshore wind refused14 of 1945%
Battery storage refused2 of 716%
Median time from submission to decision34.6 weeks17.0 weeks
Appeals lodged / allowed9 / 9—

Other large projects within 10 km

ProjectTypeMWStatuskm
Greenmoor Bankbattery storage50refused0.7
Greaves Solar Farmsolar farm5operational1.8
Armistead Wind Farmwind farm12operational2.6
Killington Wind Farmwind farm10.2abandoned4.0
Lambrigg Wind Farmwind farm6.5operational4.9
Firbank Wind Farmwind farm9.7refused6.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.2953, -2.6629).