Kirkby Moor Repowering (18 MW wind farm)

Kirkby Moor Repowering is an 18 MW wind farm project in Westmorland and Furness, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 26 November 2015; the record was last updated on 2 December 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

18 MWwind farm
refusedstatus in REPD
2 December 2015record last updated
Westmorland and Furnesscouncil area

Planning timeline

DateStage
28 February 2015Application submitted
26 November 2015Refused by the planning authority

Project details

Technology
wind farm
Capacity
18 MW
Status (REPD)
refused
Record last updated
2 December 2015
Operator or applicant
RWE Renewables
Planning authority
Westmorland and Furness
Planning application reference
SL/2014/1220
Turbines
6
Turbine height
115 m
Address (REPD)
Land at Kirkby Moor Wind Farm, Kirkby-In-Furness, Cumbria
Council area (by location)
Westmorland and Furness
Time to decision
39 weeks
REPD reference
3637

Who decides

ApplicationsWestmorland and FurnessUK
Decided applications (solar, wind, battery)6810,236
Refused30 (44%)19%
Solar refused14 of 4212%
Onshore wind refused14 of 1945%
Battery storage refused2 of 716%
Median time from submission to decision34.6 weeks17.0 weeks
Appeals lodged / allowed9 / 9—

Other large projects within 10 km

ProjectTypeMWStatuskm
Gunson Height Wind Farmwind farm7.8refused1.3
Furness Wind Farm/High Winds (Harlock Repowering)wind farm11.5operational3.4
Hill Solar Farmsolar farm5application withdrawn7.0
Solar Farm at Bleabeck Solar Farmsolar farm10application submitted7.7
Roanhead Farmsolar farm6.5operational8.1
Bleabeck Solar Farmsolar farm10application submitted8.7
Langthwaite Farmwind farm12application submitted10.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.2391, -3.1529).