What Barrow-in-Furness knows as the Walney wind farm is split into three records in the REPD: Walney 1, Walney 2 and Walney 3, 1,027 MW between them, all operated by Orsted (formerly Dong Energy). Walney 1 came first: its 51 turbines of 3.6 MW have been operational since 30 May 2011.
One application for two, a separate one for the third
Walney 1 and Walney 2 went through a single application dated 31 March 2006 and received one Section 36 consent (the register credits the decision to DECC) on 7 November 2007: 84 weeks against a median of 95.8. Construction of Walney 1 began on 10 March 2010, and Walney 2, at 184 MW, started up a year later, on 6 April 2012. Walney 3 is a separate project: application on 30 July 2013, consent after 66 weeks, 87 turbines (40 at 8 MW and 47 at 7 MW, according to Orsted; the REPD lists 110 at 6 MW), 659 MW operational since 13 September 2018. Around Walney 1, within 30 km, other companies' wind farms are running too: West of Duddon Sands (389 MW, 7.0 km), Ormonde (150 MW) and Barrow. The nearest district on land: LA14.