Energy Projects Near You

Solar, wind and battery projects near Fleetwood (FY7)

10 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of FY7 (Wyre): 7 approved but not yet running, 1 operational. The largest live scheme is Bristol Avenue (25 MW battery storage, approved on 11 May 2021, not yet built; REPD status may be out of date), 7.4 km away. Offshore, 4 wind farms are recorded within 40 km; the nearest is Barrow (90 MW, operational), 19.6 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10projects within 10 km
0awaiting a decision
7approved, not running
1operational

Projects within 10 km of FY7

Projects of 1 MW and more (6)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Fleetwood Water Treatment Worksrooftop solarrooftop solar1.3operationalupdated Jun 2016Jul 2014granted Nov 2014Jun 2016Wyre1.0
Land Hill Farmsolar farmsolar farm2.5permission expiredupdated Nov 2019Aug 2015granted Nov 2015Nov 2019Wyre7.2
Bristol Avenuebattery storagebattery storage25approved, not built may be out of dateupdated May 2021Jan 2021granted May 2021May 2021Blackpool7.4
Foxfield Nurseries, School Lanesolar farmsolar farm1.2approved, not builtupdated Jul 2025Dec 2024granted Jul 2025Jul 2025Wyre7.8
Aldon Roadbattery storagebattery storage6permission expiredupdated Jun 2020Sep 2017granted Dec 2017Jun 2020Wyre8.8
Cocker Avenue Energy storage facilitybattery storagebattery storage7.5approved, not built may be out of dateupdated May 2021Apr 2021granted Jun 2021May 2021Wyre8.9
Smaller schemes under 1 MW, mostly rooftop solar (4)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Archway Travel, Copse Roadbattery storagebattery storage—approved, not built may be out of dateupdated Jul 2023Mar 2023granted Jun 2023Jul 2023Wyre0.9
Victrex Plant, Hillhouse International Worksrooftop solarrooftop solar0.4approved, not builtupdated Oct 2024Aug 2024granted Sep 2024Oct 2024Wyre3.9
Moors Farm, Hambletonrooftop solarrooftop solar0.2approved, not builtupdated Jul 2025May 2025granted Jul 2025Jul 2025Wyre7.6
Unity College, Warbreck Hill Roadrooftop solarrooftop solar0.2approved, not builtupdated Sep 2025Jul 2025granted Sep 2025Sep 2025Blackpool9.0

Distance from the average position of the FY7 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm201001.2
Rooftop solar403100.8
Battery storage4030032.5

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
Barrow90operationalupdated Nov 201719.6
West of Duddon Sands389operationalupdated Aug 202029.5
Ormonde Offshore150operationalupdated Aug 201733.0
Walney 1184operationalupdated Sep 202034.8

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How Wyre decides solar, wind and battery applications

ApplicationsWyreUK
Decided applications (solar, wind, battery)1910,236
Refused4 (21%)19%
Solar refused1 of 1112%
Onshore wind refused3 of 445%
Battery storage refused0 of 416%
Median time from submission to decision19.4 weeks17.0 weeks
Appeals lodged / allowed0 / 2—

All projects in Wyre

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near FY7, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.