Energy Projects Near You

Bristol Avenue (25 MW battery storage)

Bristol Avenue is a 25 MW battery storage project in Blackpool, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 11 May 2021, not yet built; the record was last updated on 17 May 2021. REPD also records that the planning permission expired on 11 May 2024, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

25 MWbattery storage
approved, not builtmay be out of datestatus in REPD
17 May 2021record last updated
Blackpoolcouncil area

REPD also records that the planning permission expired on 11 May 2024, so the project may not go ahead in this form.

Planning timeline

DateStage
21 January 2021Application submitted
11 May 2021Planning permission granted
11 May 2024Permission expired

Project details

Technology
battery storage (stand-alone storage)
Capacity
25 MW
Status (REPD)
approved, not built
Record last updated
17 May 2021
Operator or applicant
Henco International Limited
Planning authority
Blackpool
Planning application reference
21/0246
Address (REPD)
281 BRISTOL AVENUE, BLACKPOOL,
Council area (by location)
Blackpool
Time to decision
16 weeks
Name in REPD
Bristol Avenue - Battery Energy Storage Facility
REPD reference
8809

Who decides

Blackpool has 7 decided solar, wind or battery applications in REPD — too few for a refusal rate (we show one from 10 decisions). Across all UK planning authorities 19% of 10,236 decisions were refusals.

Other large projects within 10 km

ProjectTypeMWStatuskm
Aldon Roadbattery storage6permission expired3.6
Cocker Avenue Energy storage facilitybattery storage7.5approved, not built3.7
Smithy Lane, Staining Solar PV Panels & BESSsolar farm40application submitted4.2
Cask Farmsolar farm5refused6.5
Peel Roadbattery storage20approved, not built8.1
Peel Road Phase 2 Solar Farmsolar farm13application submitted8.1
Lawns Solar Farmsolar farm25approved, not built9.3
Lowland Farm, Peel Roadbattery storage100application submitted9.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.8495, -3.0284).