Energy Projects Near You

Solar, wind and battery projects near Southport (PR9)

8 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of PR9 (Sefton): 5 approved but not yet running, 1 operational. The largest live scheme is Huntapac Produce Limited, Blackgate Lane (1.3 MW rooftop solar, approved on 10 February 2023, not yet built; REPD status may be out of date), 7.0 km away. Offshore, 2 wind farms are recorded within 40 km; the nearest is Burbo Bank (90 MW, operational), 23.9 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8projects within 10 km
0awaiting a decision
5approved, not running
1operational

Projects within 10 km of PR9

Projects of 1 MW and more (4)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Crossens Pumping Stationsolar farmsolar farm1approved, not built may be out of dateupdated Feb 2023Aug 2021granted Feb 2022Feb 2023Sefton1.4
Lower House Farmsolar farmsolar farm1.9refusedupdated Jan 2016Jul 2015refused Dec 2015Jan 2016West Lancashire6.1
Huntapac Produce Limited, Blackgate Lanerooftop solarrooftop solar1.3approved, not built may be out of dateupdated Feb 2023Dec 2022granted Feb 2023Feb 2023West Lancashire7.0
Ringtail Airfieldsolar farmsolar farm5application withdrawnupdated Aug 2017May 2015—Aug 2017West Lancashire9.9
Smaller schemes under 1 MW, mostly rooftop solar (4)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Crossens Pumping Stationbattery storagebattery storage—under constructionupdated Jun 2025Aug 2021granted Feb 2022Jun 2025Sefton2.5
Sainsburys Supermarketsrooftop solarrooftop solar0.6approved, not builtupdated Feb 2024Dec 2023granted Feb 2024Feb 2024Sefton2.7
Dunes, Esplanaderooftop solarrooftop solar0.2approved, not builtupdated Jan 2026Oct 2025granted Dec 2025Jan 2026Sefton3.8
Ainsdale Wastewater Treatment Workssolar farmsolar farm0.3operationalupdated Sep 2019Dec 2018granted Mar 2019Sep 2019Sefton8.6

Distance from the average position of the PR9 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm401111
Rooftop solar303002.1
Battery storage101000

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
Burbo Bank90operationalupdated Feb 201823.9
Burbo Bank Extension (Burbo Bank 2)258operationalupdated May 201828.2

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How Sefton decides solar, wind and battery applications

ApplicationsSeftonUK
Decided applications (solar, wind, battery)4010,236
Refused4 (10%)19%
Solar refused3 of 3312%
Onshore wind refused0 of 245%
Battery storage refused1 of 516%
Median time from submission to decision7.7 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

All projects in Sefton

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near PR9, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.