Energy Projects Near You

Clifton Marsh Farm, Preston New Road Solar Farm (49.9 MW)

Clifton Marsh Farm, Preston New Road Solar Farm is a 49.9 MW solar farm project in Fylde, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 22 July 2024, no decision recorded; the record was last updated on 16 August 2024. The application was submitted more than two years ago and is still shown as pending; it may have been decided since. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
application submittedmay be out of datestatus in REPD
16 August 2024record last updated
Fyldecouncil area

The application was submitted more than two years ago and is still shown as pending; it may have been decided since. 32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided.

Planning timeline

DateStage
22 July 2024Application submitted

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
application submitted
Record last updated
16 August 2024
Operator or applicant
Vattenfall
Planning authority
Fylde
Planning application reference
24/0414
Site area
68.7 ha
Address (REPD)
Clifton Marsh Farm, Preston New Road, Newton With Clifton, Preston
Council area (by location)
Fylde
Name in REPD
Clifton Marsh Farm, Preston New Road - Solar Farm
REPD reference
13763

Who decides

ApplicationsFyldeUK
Decided applications (solar, wind, battery)1910,236
Refused3 (16%)19%
Solar refused3 of 1612%
Battery storage refused0 of 316%
Median time from submission to decision19.3 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Oakfield Farmsolar farm5operational1.6
Cooper House Farmsolar farm5operational3.9
Penwortham Sub Stationbattery storage50permission expired4.1
Penworthambattery storage57approved, not built4.2
Howick Hall Farmbattery storage49.9application submitted4.6
Newfold Solar Farmsolar farm5abandoned4.9
Lower House Farm, Lewth Lane Solar Farmsolar farm20approved, not built7.6
Land off Moss Side Lanesolar farm5operational7.6
The Glowhousebattery storage5under construction9.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.758, -2.8179).