Energy Projects Near You

Penwortham (57 MW battery storage)

Penwortham is a 57 MW battery storage project in South Ribble, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 29 April 2022, not yet built; the record was last updated on 10 May 2022. REPD also records that the planning permission expired on 3 May 2025, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

57 MWbattery storage
approved, not builtmay be out of datestatus in REPD
10 May 2022record last updated
South Ribblecouncil area

REPD also records that the planning permission expired on 3 May 2025, so the project may not go ahead in this form.

Planning timeline

DateStage
1 April 2022Application submitted
29 April 2022Planning permission granted
3 May 2025Permission expired

Project details

Technology
battery storage (stand-alone storage)
Capacity
57 MW
Status (REPD)
approved, not built
Record last updated
10 May 2022
Operator or applicant
Shaw-Energi Limited
Planning authority
South Ribble
Planning application reference
07/2022/00021/FUL
Address (REPD)
Electricity Sub Station 210M From National Grid Sub Station, Howick Cross Lane 4M From Unn Howick Cross Lane Penwortham
Council area (by location)
South Ribble
Time to decision
4 weeks
Name in REPD
Penwortham - Battery storage
REPD reference
11217

Who decides

ApplicationsSouth RibbleUK
Decided applications (solar, wind, battery)1310,236
Refused0 (0%)19%
Solar refused0 of 912%
Battery storage refused0 of 416%
Median time from submission to decision6.0 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Penwortham Sub Stationbattery storage50permission expired0.1
Howick Hall Farmbattery storage49.9application submitted0.4
Clifton Marsh Farm, Preston New Road Solar Farmsolar farm49.9application submitted4.2
Oakfield Farmsolar farm5operational4.5
The Glowhousebattery storage5under construction5.8
Cooper House Farmsolar farm5operational8.2
Newfold Solar Farmsolar farm5abandoned9.1
Lower House Farm, Lewth Lane Solar Farmsolar farm20approved, not built9.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.7466, -2.7563).