Energy Projects Near You

Wanes Blades Road Solar Farm (16 MW)

Wanes Blades Road Solar Farm is a 16 MW solar farm project in West Lancashire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 17 November 2014; the record was last updated on 30 May 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

16 MWsolar farm
refusedstatus in REPD
30 May 2016record last updated
West Lancashirecouncil area

Planning timeline

DateStage
24 July 2014Application submitted
17 November 2014Refused by the planning authority
13 May 2015Appeal lodged
5 August 2015Secretary of State intervened
21 January 2016Appeal refused
21 January 2016Secretary of State refused

Project details

Technology
solar farm
Capacity
16 MW
Status (REPD)
refused
Record last updated
30 May 2016
Operator or applicant
Green Switch Solutions
Planning authority
West Lancashire
Planning application reference
2014/0791/FUL
Appeal reference
APP/P2365/W/15/3011997
Address (REPD)
Land To The East Of Wanes Blades Road, Lathom
Council area (by location)
West Lancashire
Time to decision
17 weeks
REPD reference
1206

Who decides

ApplicationsWest LancashireUK
Decided applications (solar, wind, battery)2410,236
Refused6 (25%)19%
Solar refused5 of 1612%
Onshore wind refused1 of 345%
Battery storage refused0 of 516%
Median time from submission to decision11.4 weeks17.0 weeks
Appeals lodged / allowed4 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Unit 5 XL Business Parkbattery storage49.9under construction4.2
Avondale Nurseries, Spa Lanebattery storage320approved, not built4.4
Ringtail Airfieldsolar farm5application withdrawn5.0
Vause Farmbattery storage20approved, not built7.1
Charnock Richardbattery storage30operational7.1
Thompson House Equestrian farmsolar farm5operational7.2
Pikelaw Placebattery storage10permission expired7.4
Tontine Roadbattery storage70application submitted8.4
Far Moorbattery storage50application submitted9.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.5988, -2.7925).