Energy Projects Near You

Solar, wind and battery projects near Prescot (L35)

74 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of L35 (Knowsley): 6 are waiting for a planning decision, 48 approved but not yet running, 6 operational. The largest live scheme is Perimeter Road, Kirkby (165 MW battery storage, application submitted on 14 November 2025, no decision recorded), 8.7 km away. Offshore, 2 wind farms are recorded within 40 km; the nearest is Burbo Bank (90 MW, operational), 27.8 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

74projects within 10 km
6awaiting a decision
48approved, not running
6operational

Projects within 10 km of L35

Projects of 1 MW and more (33)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Sutton Manorbattery storagebattery storage57approved, not built may be out of dateupdated Jun 2022Jun 2022granted Sep 2022Jun 2022St. Helens3.1
Burtonhead Roadbattery storagebattery storage30abandonedupdated Feb 2019Oct 2017—Feb 2019St. Helens4.5
Biffa Electricity Generating Compound, Burtonhead Roadbattery storagebattery storage1approved, not built may be out of dateupdated Nov 2022Aug 2022granted Oct 2022Nov 2022St. Helens4.5
College Streetrooftop solarrooftop solar1.2approved, not builtupdated Jul 2024May 2024granted Jun 2024Jul 2024St. Helens6.0
St Michaels Road, Ditton Roadbattery storagebattery storage14approved, not builtupdated Nov 2023Nov 2022granted Oct 2023Nov 2023Halton6.4
Ditton Road Solar Microgridsolar farmsolar farm4approved, not builtupdated Feb 2026Jun 2024granted Jan 2025Feb 2026Halton6.4
Cut Lanebattery storagebattery storage57application submittedupdated Jun 2025Apr 2025—Jun 2025Knowsley7.0
Hedco, Desoto Roadsolar farmsolar farm3.5approved, not builtupdated May 2026May 2022granted Jun 2024May 2026Halton7.3
Coopers Lane, Kirkbybattery storagebattery storage49.5approved, not builtupdated May 2024Jul 2023granted Apr 2024May 2024Knowsley7.4
Mowcroft Solar Farmsolar farmsolar farm27.1refusedupdated Dec 2025Jul 2025refused Oct 2025Dec 2025Warrington7.4
Ford Halewood Transmissions Spekere, Boulevardsolar farmsolar farm1.3approved, not builtupdated Dec 2023Jul 2023granted Dec 2023Dec 2023Knowsley7.5
Johnson's Lane - Haltonsolar farmsolar farm3.5abandonedupdated Jun 2019Jun 2015granted Oct 2015Jun 2019Halton7.7
Fiddlers Ferry Power Stationbattery storagebattery storage150under constructionupdated Mar 2024Jul 2022granted Jun 2023Mar 2024Warrington7.9
Jaguar Land Rover Jaguar Plant, North Roadrooftop solarrooftop solar9.3approved, not builtupdated Mar 2025Dec 2024granted Feb 2025Mar 2025Knowsley7.9
Larkins Farm, Gellings Lane Solar Farmsolar farmsolar farm1.5refusedupdated Aug 2024Oct 2023refused Jul 2024Aug 2024Knowsley7.9
Johnson's Lane - Warringtonsolar farmsolar farm1.5abandonedupdated Jun 2019Jun 2015granted Feb 2016Jun 2019Halton8.1
The Hut Group, Skyline Driverooftop solarrooftop solar6.8approved, not builtupdated Jul 2025May 2025granted Jul 2025Jul 2025Warrington8.3
The Hut Group, Skyline Driverooftop solarrooftop solar1.5approved, not builtupdated Dec 2025Sep 2025granted Nov 2025Dec 2025Warrington8.3
Amazon Omega Business Parkrooftop solarrooftop solar1.5operationalupdated Jan 2020Feb 2019granted Apr 2019Jan 2020Warrington8.3
Land South Of Joy Lanesolar farmsolar farm5refusedupdated Sep 2015May 2015refused Aug 2015Sep 2015Warrington8.3
Lockheed Road, Burtonwood & Westbrookrooftop solarrooftop solar1.8approved, not builtupdated Aug 2023Jun 2023granted Aug 2023Aug 2023Warrington8.3
Charleywood Road, Knowsley Industrial Parkbattery storagebattery storage49.9abandonedupdated Sep 2022Oct 2017—Sep 2022Knowsley8.6
Perimeter Road, Kirkbybattery storagebattery storage165application submittedupdated Dec 2025Nov 2025—Dec 2025Knowsley8.7
Fairchild Road, Burtonwood & Westbrookrooftop solarrooftop solar1approved, not builtupdated Nov 2023Jul 2023granted Oct 2023Nov 2023Warrington8.8
Battery Energy Storage Systembattery storagebattery storage6approved, not builtupdated May 2025Nov 2024granted Apr 2025May 2025Liverpool9.0
Liverpool John Lennon Airport Solar Farmsolar farmsolar farm3refusedupdated Jan 2022Dec 2021refused Jun 2022Jan 2022Liverpool9.1
D H L Exel Supply Chain Burton Foods, Portal Wayrooftop solarrooftop solar1application submitted may be out of dateupdated Jul 2023Jun 2023—Jul 2023Liverpool9.2
Station Road, Fiddlers Ferrybattery storagebattery storage250refusedupdated Dec 2025Jul 2025refused Dec 2025Dec 2025Warrington9.3
Lister Drivebattery storagebattery storage49.9operationalupdated Jan 2023Feb 2020granted Mar 2021Jan 2023Liverpool9.5
Liverpool Energy Management Facilitybattery storagebattery storage49.9operationalupdated Mar 2022Feb 2020granted Nov 2020Mar 2022Liverpool9.5
Carnegie Road (Phase 2)battery storagebattery storage40permission expiredupdated Jun 2019Mar 2019granted Dec 2019Jun 2019Liverpool9.5
Land at Carnegie Roadbattery storagebattery storage20operationalupdated Jan 2019Nov 2016—Jan 2019Liverpool9.5
Land south of 50 Station Roadsolar farmsolar farm5refusedupdated Sep 2015May 2015refused Aug 2015Sep 2015Warrington9.6
Smaller schemes under 1 MW, mostly rooftop solar (41)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Whiston Hospital, Warrington Roadrooftop solarrooftop solar0.2approved, not builtupdated Apr 2026Oct 2025granted Dec 2025Apr 2026Knowsley0.7
Lea Green Business Park, Eurolinkrooftop solarrooftop solar0.3approved, not builtupdated Aug 2025May 2025granted Jul 2025Aug 2025St. Helens2.8
Lea Green Business Park, Eurolinkrooftop solarrooftop solar0.6approved, not builtupdated Jul 2024May 2024granted Jun 2024Jul 2024St. Helens2.8
Earlsfield Park, Arley Driverooftop solarrooftop solar0.1application submittedupdated Feb 2025Jan 2025—Feb 2025Knowsley3.2
Mere Grange, Leasiderooftop solarrooftop solar0.2approved, not builtupdated Jun 2025Apr 2025granted Jun 2025Jun 2025St. Helens3.2
The Sutton Academy, Elton Head Roadrooftop solarrooftop solar0.4approved, not builtupdated Sep 2025Jul 2025granted Sep 2025Sep 2025St. Helens3.8
Arnold Clark Renault, Delphwood Driverooftop solarrooftop solar0.2approved, not builtupdated May 2026Feb 2026granted Mar 2026May 2026St. Helens4.9
Queens Park Health And Fitnessrooftop solarrooftop solar0.3approved, not builtupdated Feb 2025Dec 2024granted Feb 2025Feb 2025St. Helens5.0
DTC St Helens Hospital, Marshalls Cross Roadrooftop solarrooftop solar0.2refusedupdated May 2024Mar 2024refused May 2024May 2024St. Helens5.2
Rivendell Nurseriesrooftop solarrooftop solar0.2application submittedJun 2026——Halton5.4
St Helens Rugby League Stadium, Peasley Cross Lanerooftop solarrooftop solar0.4approved, not builtupdated Mar 2023Nov 2022granted Jan 2023Mar 2023St. Helens5.4
Halewood Leisure Centre, Baileys Lanerooftop solarrooftop solar0.3approved, not builtupdated Dec 2024Oct 2024granted Nov 2024Dec 2024Knowsley6.2
Halewood Leisure Centre, Baileys Lanerooftop solarrooftop solar0.3approved, not builtupdated Sep 2024Jul 2024granted Aug 2024Sep 2024Knowsley6.2
Peter Gilding And Company, Caddick Roadrooftop solarrooftop solar0.5approved, not builtupdated Dec 2024Oct 2024granted Dec 2024Dec 2024Knowsley7.1
Adlib House, Kitling Roadrooftop solarrooftop solar0.2approved, not builtupdated Oct 2023Aug 2023granted Sep 2023Oct 2023Knowsley7.2
Omega West, St Helens, Unit 4, Zone 8rooftop solarrooftop solar0.7application withdrawnupdated Feb 2025Nov 2024—Feb 2025St. Helens7.3
Sutton International, Gorsey Lane Solar PV Arraysrooftop solarrooftop solar—approved, not builtupdated Jan 2025Oct 2024granted Dec 2024Jan 2025Halton7.5
Sainsburys Supermarket, East Prescot Roadrooftop solarrooftop solar0.5approved, not builtupdated Jul 2025May 2025granted Jun 2025Jul 2025Liverpool7.6
Penrhyn Court, Penrhyn Roadrooftop solarrooftop solar0.3approved, not builtupdated May 2026Jan 2026granted Feb 2026May 2026Knowsley7.6
Beverston Engineering, Unit Brooftop solarrooftop solar0.2approved, not builtupdated Nov 2025Jul 2025granted Sep 2025Nov 2025Knowsley7.6
Alder Hey Hospital, East Prescot Roadrooftop solarrooftop solar0.5approved, not builtupdated Jun 2026Jan 2026granted Mar 2026Jun 2026Liverpool7.7
Haweswater Car Park Solar Canopysolar farmsolar farm0.9approved, not builtupdated Oct 2024May 2024granted Oct 2024Oct 2024Warrington7.8
Jaguar Land Rover, North Road - Ground Mounted Solar Panelssolar farmsolar farm—approved, not builtupdated Mar 2025Jan 2025granted Mar 2025Mar 2025Knowsley7.9
Leisure United Simpson - Micro Energy Storage Systembattery storagebattery storage0.2approved, not builtupdated Nov 2025Jul 2025granted Sep 2025Nov 2025Liverpool8.0
Renaissance Way - Plot 7 Solar PV Arrayrooftop solarrooftop solar—approved, not builtupdated Jan 2024Oct 2023granted Dec 2023Jan 2024Liverpool8.2
Knowsley Industrial Parkrooftop solarrooftop solar0.3approved, not builtupdated Apr 2022Nov 2020granted Jan 2021Apr 2022Knowsley8.2
City Plumbing, Lockheed Roadrooftop solarrooftop solar0.6approved, not builtupdated Jul 2024Apr 2024granted Jun 2024Jul 2024Warrington8.3
Dominos Pizza, Skyline Driverooftop solarrooftop solar1approved, not builtupdated Feb 2023Jan 2023granted Feb 2023Feb 2023Warrington8.5
Charley Wood Road, Knowsley Industrial Park Solar Photovoltaicsrooftop solarrooftop solar0.9approved, not builtupdated Oct 2023Sep 2023granted Oct 2023Oct 2023Knowsley8.6
The Big Yellow Self Storage, Mill Lanerooftop solarrooftop solar0.2approved, not builtupdated May 2023Apr 2023granted May 2023May 2023Liverpool8.7
Self Storage Liverpool South, Goodlass Roadrooftop solarrooftop solar0.2approved, not builtupdated Jul 2025Apr 2025granted Jun 2025Jul 2025Liverpool8.8
Leiria Way Car Parkbattery storagebattery storage—operationalupdated Feb 2021Feb 2020granted May 2020Feb 2021Halton8.8
Dixons Croxteth Academy, Carr Lane Eastrooftop solarrooftop solar0.2approved, not builtupdated Nov 2025Jul 2025granted Oct 2025Nov 2025Liverpool8.9
Henry Diaper, Knowsley Industrial Parkrooftop solarrooftop solar0.2application submitted may be out of dateupdated May 2023May 2023—May 2023Knowsley9.0
IBL Cold Stores Solar Photovoltaics Panelsrooftop solarrooftop solar0.8operationalupdated Oct 2021Oct 2021granted Feb 2022Oct 2021Knowsley9.0
Moss End Way, Kirkby Knowsleybattery storagebattery storage0.2refusedupdated Jun 2026Dec 2025refused Apr 2026Jun 2026Knowsley9.1
David Lloyd Leisure, Arbour Lanerooftop solarrooftop solar—approved, not builtupdated Aug 2023Jun 2023granted Aug 2023Aug 2023Knowsley9.3
Stanley Meat Market, Prescot Road Solar PV Systemsrooftop solarrooftop solar0.3approved, not builtupdated Sep 2024Jul 2024granted Jul 2024Sep 2024Liverpool9.4
Speke Hall Avenuebattery storagebattery storage—approved, not builtupdated Mar 2025Dec 2023granted Feb 2025Mar 2025Liverpool9.6
Bellerophon Way Tescorooftop solarrooftop solar0.4approved, not built may be out of dateupdated Sep 2020Mar 2019granted May 2019Sep 2020St. Helens9.6
Starbank Panel Products, Junction Lanerooftop solarrooftop solar0.5approved, not builtupdated Nov 2022Aug 2022granted Oct 2022Nov 2022St. Helens10.0

Distance from the average position of the L35 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm1205059.6
Rooftop solar434352133
Battery storage192842500

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
Burbo Bank90operationalupdated Feb 201827.8
Burbo Bank Extension (Burbo Bank 2)258operationalupdated May 201833.0

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How Knowsley decides solar, wind and battery applications

ApplicationsKnowsleyUK
Decided applications (solar, wind, battery)2010,236
Refused5 (25%)19%
Solar refused4 of 1812%
Battery storage refused1 of 216%
Median time from submission to decision7.4 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

UK: all UK planning authorities. Counted under these REPD planning authority names: Knowsley, Knowsley Borough.

All projects in Knowsley

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near L35, 5 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.