Energy Projects Near You

Jaguar Land Rover Jaguar Plant, North Road (9.3 MW rooftop solar)

Jaguar Land Rover Jaguar Plant, North Road is a 9.3 MW rooftop solar project in Knowsley, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 25 February 2025, not yet built; the record was last updated on 4 March 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

9.3 MWrooftop solar
approved, not builtstatus in REPD
4 March 2025record last updated
Knowsleycouncil area

Planning timeline

DateStage
3 December 2024Application submitted
25 February 2025Planning permission granted

Project details

Technology
rooftop solar
Capacity
9.3 MW
Status (REPD)
approved, not built
Record last updated
4 March 2025
Operator or applicant
Jaguar Land Rover
Planning authority
Knowsley
Planning application reference
24/00659/PDS
Address (REPD)
Jaguar Land Rover Jaguar Plant North Road Halewood
Council area (by location)
Knowsley
Time to decision
12 weeks
Name in REPD
Jaguar Land Rover Jaguar Plant, North Road - Solar Panels
REPD reference
17836

Who decides

ApplicationsKnowsleyUK
Decided applications (solar, wind, battery)2010,236
Refused5 (25%)19%
Solar refused4 of 1812%
Battery storage refused1 of 216%
Median time from submission to decision7.4 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

UK: all UK planning authorities. Counted under these REPD planning authority names: Knowsley, Knowsley Borough.

Other large projects within 10 km

ProjectTypeMWStatuskm
St Michaels Road, Ditton Roadbattery storage14approved, not built4.9
Frodsham Marshwind farm50.4operational7.1
Cheshire Power Stationbattery storage45approved, not built7.8
Land At Elton Farmsolar farm5application submitted8.1
Oil Sites Roadbattery storage9.6approved, not built8.2
Eastham Balacing Services Plantbattery storage27application withdrawn8.4
Frodsham Solar Project & Battery Storagesolar farm147application submitted8.5
Cholmondeley Roadbattery storage150approved, not built8.9
Battery Energy Storage Systembattery storage6approved, not built9.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.3504, -2.8346).