Energy Projects Near You

Solar, wind and battery projects near Liverpool (L24)

45 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of L24 (Liverpool): 6 are waiting for a planning decision, 31 approved but not yet running, 3 operational. The largest live scheme is Cholmondeley Road (150 MW battery storage, approved on 10 August 2022, not yet built; REPD status may be out of date), 8.9 km away. Offshore, 2 wind farms are recorded within 40 km; the nearest is Burbo Bank (90 MW, operational), 28.0 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

45projects within 10 km
6awaiting a decision
31approved, not running
3operational

Projects within 10 km of L24

Projects of 1 MW and more (19)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Jaguar Land Rover Jaguar Plant, North Roadrooftop solarrooftop solar9.3approved, not builtupdated Mar 2025Dec 2024granted Feb 2025Mar 2025Knowsley0.8
Liverpool John Lennon Airport Solar Farmsolar farmsolar farm3refusedupdated Jan 2022Dec 2021refused Jun 2022Jan 2022Liverpool0.9
Ford Halewood Transmissions Spekere, Boulevardsolar farmsolar farm1.3approved, not builtupdated Dec 2023Jul 2023granted Dec 2023Dec 2023Knowsley1.3
Ditton Road Solar Microgridsolar farmsolar farm4approved, not builtupdated Feb 2026Jun 2024granted Jan 2025Feb 2026Halton5.3
St Michaels Road, Ditton Roadbattery storagebattery storage14approved, not builtupdated Nov 2023Nov 2022granted Oct 2023Nov 2023Halton5.4
Hedco, Desoto Roadsolar farmsolar farm3.5approved, not builtupdated May 2026May 2022granted Jun 2024May 2026Halton6.2
Frodsham Marshwind farmwind farm50.4operationalupdated May 2018Feb 2010granted Oct 2012May 2018Cheshire West and Chester6.7
Cheshire Power Stationbattery storagebattery storage45approved, not built may be out of dateupdated Dec 2021Nov 2021granted May 2023Dec 2021Cheshire West and Chester7.0
Oil Sites Roadbattery storagebattery storage9.6approved, not built may be out of dateupdated Apr 2020Aug 2017granted Oct 2017Apr 2020Cheshire West and Chester7.3
Land At Elton Farmsolar farmsolar farm5application submitted may be out of dateupdated Jul 2015May 2015—Jul 2015Cheshire West and Chester7.5
Jaguar Landrover Phoenix Building, Eric Foundation Roadrooftop solarrooftop solar1.3approved, not builtupdated May 2025Feb 2025granted Apr 2025May 2025Cheshire West and Chester7.5
Eastham Balacing Services Plantbattery storagebattery storage27application withdrawnupdated Nov 2018Oct 2017—Nov 2018Wirral7.8
Frodsham Solar Project & Battery Storagesolar farmsolar farm147application submittedupdated Oct 2025May 2025—Oct 2025Cheshire West and Chester8.3
Frodsham Solar Project & Battery Storagebattery storagebattery storage100application submittedupdated Oct 2025May 2025—Oct 2025Cheshire West and Chester8.3
Cholmondeley Roadbattery storagebattery storage150approved, not built may be out of dateupdated Mar 2026Sep 2021granted Aug 2022Mar 2026Halton8.9
Hob Lane, Dunham On The Hill Solar Farmsolar farmsolar farm30application submittedupdated Jul 2025May 2025—Jul 2025Cheshire West and Chester9.5
Land off, Common Lanesolar farmsolar farm5refused on appealupdated May 2016Apr 2015refused Oct 2015May 2016Cheshire West and Chester9.5
Johnson's Lane - Haltonsolar farmsolar farm3.5abandonedupdated Jun 2019Jun 2015granted Oct 2015Jun 2019Halton9.7
Battery Energy Storage Systembattery storagebattery storage6approved, not builtupdated May 2025Nov 2024granted Apr 2025May 2025Liverpool9.7
Smaller schemes under 1 MW, mostly rooftop solar (26)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Renaissance Way - Plot 7 Solar PV Arrayrooftop solarrooftop solar—approved, not builtupdated Jan 2024Oct 2023granted Dec 2023Jan 2024Liverpool0.8
Jaguar Land Rover, North Road - Ground Mounted Solar Panelssolar farmsolar farm—approved, not builtupdated Mar 2025Jan 2025granted Mar 2025Mar 2025Knowsley0.8
Speke Hall Avenuebattery storagebattery storage—approved, not builtupdated Mar 2025Dec 2023granted Feb 2025Mar 2025Liverpool1.6
Self Storage Liverpool South, Goodlass Roadrooftop solarrooftop solar0.2approved, not builtupdated Jul 2025Apr 2025granted Jun 2025Jul 2025Liverpool2.4
Estuary Boulevardrooftop solarrooftop solar0.6approved, not builtupdated Apr 2024Jan 2024granted Mar 2024Apr 2024Liverpool2.4
Halewood Leisure Centre, Baileys Lanerooftop solarrooftop solar0.3approved, not builtupdated Dec 2024Oct 2024granted Nov 2024Dec 2024Knowsley2.5
Halewood Leisure Centre, Baileys Lanerooftop solarrooftop solar0.3approved, not builtupdated Sep 2024Jul 2024granted Aug 2024Sep 2024Knowsley2.5
Garston Shore Roadrooftop solarrooftop solar0.5approved, not built may be out of dateupdated Aug 2022Jun 2022granted Sep 2022Aug 2022Liverpool2.9
Leisure United Simpson - Micro Energy Storage Systembattery storagebattery storage0.2approved, not builtupdated Nov 2025Jul 2025granted Sep 2025Nov 2025Liverpool2.9
Leisure United Jericho Lane - Micro Energy Storage Systembattery storagebattery storage0.2approved, not builtupdated Nov 2025Jul 2025granted Aug 2025Nov 2025Liverpool7.2
Leiria Way Car Parkbattery storagebattery storage—operationalupdated Feb 2021Feb 2020granted May 2020Feb 2021Halton7.2
Ash Road, Eltonbattery storagebattery storage—application withdrawnupdated Jun 2026Dec 2023—Jun 2026Cheshire West and Chester7.5
Aigburth Parkrooftop solarrooftop solar—approved, not builtupdated Apr 2021Feb 2021granted May 2021Apr 2021Liverpool8.2
Sainsburys Supermarket, East Prescot Roadrooftop solarrooftop solar0.5approved, not builtupdated Jul 2025May 2025granted Jun 2025Jul 2025Liverpool8.9
The Big Yellow Self Storage, Mill Lanerooftop solarrooftop solar0.2approved, not builtupdated May 2023Apr 2023granted May 2023May 2023Liverpool9.0
Sutton International, Gorsey Lane Solar PV Arraysrooftop solarrooftop solar—approved, not builtupdated Jan 2025Oct 2024granted Dec 2024Jan 2025Halton9.1
Alder Hey Hospital, East Prescot Roadrooftop solarrooftop solar0.5approved, not builtupdated Jun 2026Jan 2026granted Mar 2026Jun 2026Liverpool9.3
Whiston Hospital, Warrington Roadrooftop solarrooftop solar0.2approved, not builtupdated Apr 2026Oct 2025granted Dec 2025Apr 2026Knowsley9.3
Sainsburys, Kinsey Roadrooftop solarrooftop solar0.5approved, not builtupdated Jul 2025May 2025granted Jul 2025Jul 2025Cheshire West and Chester9.3
Earlsfield Park, Arley Driverooftop solarrooftop solar0.1application submittedupdated Feb 2025Jan 2025—Feb 2025Knowsley9.5
Ellesmere Port Sports Village Solar Arraysrooftop solarrooftop solar0.3approved, not builtupdated Dec 2021Sep 2021granted Oct 2021Dec 2021Cheshire West and Chester9.5
Tesco Superstorerooftop solarrooftop solar—approved, not builtupdated Mar 2021Jan 2021granted Apr 2021Mar 2021Liverpool9.5
Biffa Waste Services, Dock Road South Battery Storage Unitsbattery storagebattery storage—approved, not built may be out of dateupdated Jan 2023Nov 2022granted Dec 2022Jan 2023Wirral9.6
Rivendell Nurseriesrooftop solarrooftop solar0.2application submittedJun 2026——Halton9.6
Longlooms Road Eastrooftop solarrooftop solar0.2operationalupdated Jun 2022Jun 2022granted Oct 2022Jun 2022Cheshire West and Chester9.7
Stanley Meat Market, Prescot Road Solar PV Systemsrooftop solarrooftop solar0.3approved, not builtupdated Sep 2024Jul 2024granted Jul 2024Sep 2024Liverpool9.9

Distance from the average position of the L24 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm103402191
Rooftop solar212181015.3
Wind farm100100
Battery storage131910325

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
Burbo Bank90operationalupdated Feb 201828.0
Burbo Bank Extension (Burbo Bank 2)258operationalupdated May 201832.3

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How Liverpool decides solar, wind and battery applications

ApplicationsLiverpoolUK
Decided applications (solar, wind, battery)2610,236
Refused0 (0%)19%
Solar refused0 of 1812%
Battery storage refused0 of 816%
Median time from submission to decision7.8 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

All projects in Liverpool

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near L24, 6 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.