Energy Projects Near You

Hob Lane, Dunham On The Hill Solar Farm (30 MW)

Hob Lane, Dunham On The Hill Solar Farm is a 30 MW solar farm project in Cheshire West and Chester, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 23 May 2025, no decision recorded; the record was last updated on 14 July 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

30 MWsolar farm
application submittedstatus in REPD
14 July 2025record last updated
Cheshire West and Chestercouncil area

Planning timeline

DateStage
23 May 2025Application submitted

Project details

Technology
solar farm
Capacity
30 MW
Status (REPD)
application submitted
Record last updated
14 July 2025
Operator or applicant
Belltown Power Limited
Planning authority
Cheshire West and Chester
Planning application reference
25/01339/FUL
Site area
77.0 ha
Address (REPD)
N/O Rake Lane, Dunham On The Hill, Frodsham
Council area (by location)
Cheshire West and Chester
Name in REPD
Hob Lane, Dunham On The Hill - Solar Farm
REPD reference
19082

Who decides

ApplicationsCheshire West and ChesterUK
Decided applications (solar, wind, battery)5410,236
Refused6 (11%)19%
Solar refused3 of 4012%
Onshore wind refused1 of 245%
Battery storage refused2 of 1216%
Median time from submission to decision10.1 weeks17.0 weeks
Appeals lodged / allowed1 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Land off, Common Lanesolar farm5refused on appeal<0.1
Land At Elton Farmsolar farm5application submitted2.2
Frodsham Marshwind farm50.4operational4.8
Oil Sites Roadbattery storage9.6approved, not built5.2
Frodsham Solar Project & Battery Storagesolar farm147application submitted6.0
Electricity Substation, Bellevue Lanebattery storage40approved, not built7.1
Portmanmoor Road Industrial Estate, Splott Battery Storage Unitsbattery storage10approved, not built7.1
Cholmondeley Roadbattery storage150approved, not built8.0
Cheshire Power Stationbattery storage45approved, not built8.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.2613, -2.7984).