Solar, wind and battery projects near Frodsham (WA6)
23 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of WA6 (Cheshire West and Chester): 8 are waiting for a planning decision, 9 approved but not yet running, 3 operational. The largest live scheme is Cholmondeley Road (150 MW battery storage, approved on 10 August 2022, not yet built; REPD status may be out of date), 4.6 km away. Offshore, 1 wind farm is recorded within 40 km; the nearest is Burbo Bank (90 MW, operational), 38.8 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of WA6
Projects of 1 MW and more (14)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Frodsham Solar Project & Battery Storagesolar farm | solar farm | 147 | application submittedupdated Oct 2025 | May 2025 | — | Oct 2025 | Cheshire West and Chester | 3.3 |
| Frodsham Solar Project & Battery Storagebattery storage | battery storage | 100 | application submittedupdated Oct 2025 | May 2025 | — | Oct 2025 | Cheshire West and Chester | 3.3 |
| Frodsham Marshwind farm | wind farm | 50.4 | operationalupdated May 2018 | Feb 2010 | granted Oct 2012 | May 2018 | Cheshire West and Chester | 4.3 |
| Cholmondeley Roadbattery storage | battery storage | 150 | approved, not built may be out of dateupdated Mar 2026 | Sep 2021 | granted Aug 2022 | Mar 2026 | Halton | 4.6 |
| Land At Elton Farmsolar farm | solar farm | 5 | application submitted may be out of dateupdated Jul 2015 | May 2015 | — | Jul 2015 | Cheshire West and Chester | 4.9 |
| Hob Lane, Dunham On The Hill Solar Farmsolar farm | solar farm | 30 | application submittedupdated Jul 2025 | May 2025 | — | Jul 2025 | Cheshire West and Chester | 5.0 |
| Land off, Common Lanesolar farm | solar farm | 5 | refused on appealupdated May 2016 | Apr 2015 | refused Oct 2015 | May 2016 | Cheshire West and Chester | 5.0 |
| Aston Grange Farmwind farm | wind farm | 12 | refused on appealupdated Nov 2011 | Jun 2005 | refused Oct 2006 | Nov 2011 | Cheshire West and Chester | 5.0 |
| Aston Grange, Aston Solar Panels & Battery Energy Storage Systemsolar farm | solar farm | 20 | application submittedupdated Mar 2025 | Feb 2025 | — | Mar 2025 | Cheshire West and Chester | 5.5 |
| Aston Grange, Aston Solar Panels & Battery Energy Storage Systembattery storage | battery storage | 6 | application submittedupdated Mar 2025 | Feb 2025 | — | Mar 2025 | Cheshire West and Chester | 5.5 |
| Hedco, Desoto Roadsolar farm | solar farm | 3.5 | approved, not builtupdated May 2026 | May 2022 | granted Jun 2024 | May 2026 | Halton | 9.0 |
| Oil Sites Roadbattery storage | battery storage | 9.6 | approved, not built may be out of dateupdated Apr 2020 | Aug 2017 | granted Oct 2017 | Apr 2020 | Cheshire West and Chester | 9.6 |
| Ditton Road Solar Microgridsolar farm | solar farm | 4 | approved, not builtupdated Feb 2026 | Jun 2024 | granted Jan 2025 | Feb 2026 | Halton | 9.8 |
| St Michaels Road, Ditton Roadbattery storage | battery storage | 14 | approved, not builtupdated Nov 2023 | Nov 2022 | granted Oct 2023 | Nov 2023 | Halton | 9.9 |
Smaller schemes under 1 MW, mostly rooftop solar (9)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Lady Heyes Camping And Caravan Site, Kingsley Roadsolar farm | solar farm | 0.4 | approved, not builtupdated Nov 2025 | Oct 2024 | granted Sep 2025 | Nov 2025 | Cheshire West and Chester | 1.8 |
| Ash Road, Eltonbattery storage | battery storage | — | application withdrawnupdated Jun 2026 | Dec 2023 | — | Jun 2026 | Cheshire West and Chester | 5.1 |
| Hosokawa Micron, Rivington Roadrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Apr 2024 | Feb 2024 | granted Apr 2024 | Apr 2024 | Halton | 6.4 |
| Phoenix Medical Supplies, Rivington Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Mar 2023 | Dec 2022 | granted Feb 2023 | Mar 2023 | Halton | 6.5 |
| Kelsall Hill Equestrian Centre, Middlewich Roadrooftop solar | rooftop solar | 0.4 | application submittedupdated Nov 2024 | Oct 2024 | — | Nov 2024 | Cheshire West and Chester | 7.5 |
| Gowy Solar Parkrooftop solar | rooftop solar | — | application submittedupdated Jan 2026 | Nov 2025 | — | Jan 2026 | Cheshire West and Chester | 7.5 |
| Leiria Way Car Parkbattery storage | battery storage | — | operationalupdated Feb 2021 | Feb 2020 | granted May 2020 | Feb 2021 | Halton | 7.7 |
| Pembroke Court, Haltonrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Jun 2026 | Mar 2026 | granted Apr 2026 | Jun 2026 | Halton | 9.7 |
| Daresbury Science Parksolar farm | solar farm | 0.6 | operationalupdated Jan 2022 | Aug 2021 | granted Jan 2022 | Jan 2022 | Halton | 9.9 |
Distance from the average position of the WA6 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 9 | 4 | 3 | 1 | 1 | 210 |
| Rooftop solar | 5 | 2 | 3 | 0 | 0 | 1.5 |
| Wind farm | 2 | 0 | 0 | 1 | 1 | 0 |
| Battery storage | 7 | 2 | 3 | 1 | 0 | 280 |
MW in pipeline: pending, approved and under-construction capacity.
Offshore wind farms within 40 km
| Wind farm | MW | Status (REPD) | km |
|---|---|---|---|
| Burbo Bank | 90 | operationalupdated Feb 2018 | 38.8 |
Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.
How Cheshire West and Chester decides solar, wind and battery applications
| Applications | Cheshire West and Chester | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 54 | 10,236 |
| Refused | 6 (11%) | 19% |
| Solar refused | 3 of 40 | 12% |
| Onshore wind refused | 1 of 2 | 45% |
| Battery storage refused | 2 of 12 | 16% |
| Median time from submission to decision | 10.1 weeks | 17.0 weeks |
| Appeals lodged / allowed | 1 / 2 | — |
All projects in Cheshire West and Chester
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near WA6, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.