Aston Grange Farm (12 MW wind farm)

Aston Grange Farm is a 12 MW wind farm project in Cheshire West and Chester, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 5 November 2008; the record was last updated on 28 November 2011.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

12 MWwind farm
refused on appealstatus in REPD
28 November 2011record last updated
Cheshire West and Chestercouncil area

Planning timeline

DateStage
20 June 2005Application submitted
11 October 2006Refused by the planning authority
5 November 2008Appeal refused

Project details

Technology
wind farm
Capacity
12 MW
Status (REPD)
refused on appeal
Record last updated
28 November 2011
Operator or applicant
Tegni Cymru
Planning authority
Cheshire West and Chester
Planning application reference
05-1059-fum
Appeal reference
V/07/00025/REF
Turbines
4
Address (REPD)
Aston Grange Farm, Acton Bridge , Cheshire
Council area (by location)
Cheshire West and Chester
Time to decision
68 weeks
REPD reference
3967

Who decides

ApplicationsCheshire West and ChesterUK
Decided applications (solar, wind, battery)5410,236
Refused6 (11%)19%
Solar refused3 of 4012%
Onshore wind refused1 of 245%
Battery storage refused2 of 1216%
Median time from submission to decision10.1 weeks17.0 weeks
Appeals lodged / allowed1 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Aston Grange, Aston Solar Panels & Battery Energy Storage Systemsolar farm20application submitted0.5
Cholmondeley Roadbattery storage150approved, not built4.6
Frodsham Solar Project & Battery Storagesolar farm147application submitted5.4
Frodsham Marshwind farm50.4operational7.5
Wallerscote Limebedsbattery storage30approved, not built8.6
Wallerscote Limebeds Solar Pv Parksolar farm22approved, not built8.6
Station Road, Fiddlers Ferrybattery storage250refused9.0
Fiddlers Ferry Power Stationbattery storage150under construction9.3
Land At Elton Farmsolar farm5application submitted9.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.2919, -2.6567).