Energy Projects Near You

Fiddlers Ferry Power Station (150 MW battery storage)

Fiddlers Ferry Power Station is a 150 MW battery storage project in Warrington, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 28 March 2024; the record was last updated on 21 March 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

150 MWbattery storage
under constructionstatus in REPD
21 March 2024record last updated
Warringtoncouncil area

Planning timeline

DateStage
27 July 2022Application submitted
20 June 2023Planning permission granted
28 March 2024Construction started

Project details

Technology
battery storage (stand-alone storage)
Capacity
150 MW
Status (REPD)
under construction
Record last updated
21 March 2024
Operator or applicant
SSE Enterprise (SSE PLC)
Planning authority
Warrington
Planning application reference
2022/41800
Address (REPD)
Fiddlers Ferry Power Station, Widnes Road, Warrington
Council area (by location)
Warrington
Time to decision
47 weeks
Name in REPD
Fiddlers Ferry Power Station - Battery storage
REPD reference
9404

Who decides

ApplicationsWarringtonUK
Decided applications (solar, wind, battery)3510,236
Refused6 (17%)19%
Solar refused5 of 3012%
Onshore wind refused0 of 145%
Battery storage refused1 of 416%
Median time from submission to decision7.9 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Mowcroft Solar Farmsolar farm27.1refused0.5
Station Road, Fiddlers Ferrybattery storage250refused1.8
Land south of 50 Station Roadsolar farm5refused2.6
The Hut Group, Skyline Driverooftop solar6.8approved, not built4.7
St Michaels Road, Ditton Roadbattery storage14approved, not built5.2
Land South Of Joy Lanesolar farm5refused5.2
Warrington Home Solar Schemerooftop solar5.3operational5.9
Sutton Manorbattery storage57approved, not built6.2
Cholmondeley Roadbattery storage150approved, not built6.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.373, -2.6879).