Energy Projects Near You

Land South Of Joy Lane (5 MW solar farm)

Land South Of Joy Lane is a 5 MW solar farm project in Warrington, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 17 August 2015; the record was last updated on 2 September 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
refusedstatus in REPD
2 September 2015record last updated
Warringtoncouncil area

Planning timeline

DateStage
20 May 2015Application submitted
17 August 2015Refused by the planning authority

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
refused
Record last updated
2 September 2015
Operator or applicant
SEP Burtonwood
Planning authority
Warrington
Planning application reference
2015/25803
Site area
6.9 ha
Address (REPD)
Land South Of, Joy Lane, And West Of Wrights Lane, Burtonwood, Warrington
Council area (by location)
Warrington
Time to decision
13 weeks
REPD reference
5304

Who decides

ApplicationsWarringtonUK
Decided applications (solar, wind, battery)3510,236
Refused6 (17%)19%
Solar refused5 of 3012%
Onshore wind refused0 of 145%
Battery storage refused1 of 416%
Median time from submission to decision7.9 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
The Hut Group, Skyline Driverooftop solar6.8approved, not built0.5
Land south of 50 Station Roadsolar farm5refused4.1
Mowcroft Solar Farmsolar farm27.1refused4.8
Station Road, Fiddlers Ferrybattery storage250refused4.8
Warrington Home Solar Schemerooftop solar5.3operational4.9
Fiddlers Ferry Power Stationbattery storage150under construction5.2
Sutton Manorbattery storage57approved, not built5.3
Burtonhead Roadbattery storage30abandoned6.0
Kenyon Lanesolar farm5refused8.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.4163, -2.6584).