Land At Elton Farm (5 MW solar farm)

Land At Elton Farm is a 5 MW solar farm project in Cheshire West and Chester, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 11 May 2015, no decision recorded; the record was last updated on 6 July 2015. The application was submitted more than two years ago and is still shown as pending; it may have been decided since. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
application submittedmay be out of datestatus in REPD
6 July 2015record last updated
Cheshire West and Chestercouncil area

The application was submitted more than two years ago and is still shown as pending; it may have been decided since. 32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided.

Planning timeline

DateStage
11 May 2015Application submitted

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
application submitted
Record last updated
6 July 2015
Operator or applicant
SEP Elton
Planning authority
Cheshire West and Chester
Planning application reference
15/01909/FUL
Address (REPD)
Land At Elton Farm, Hapsford Lane, Ince, Chester
Council area (by location)
Cheshire West and Chester
REPD reference
5300

Who decides

ApplicationsCheshire West and ChesterUK
Decided applications (solar, wind, battery)5410,236
Refused6 (11%)19%
Solar refused3 of 4012%
Onshore wind refused1 of 245%
Battery storage refused2 of 1216%
Median time from submission to decision10.1 weeks17.0 weeks
Appeals lodged / allowed1 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hob Lane, Dunham On The Hill Solar Farmsolar farm30application submitted2.2
Land off, Common Lanesolar farm5refused on appeal2.2
Frodsham Marshwind farm50.4operational2.9
Frodsham Solar Project & Battery Storagesolar farm147application submitted4.6
Oil Sites Roadbattery storage9.6approved, not built4.8
Cholmondeley Roadbattery storage150approved, not built6.6
Cheshire Power Stationbattery storage45approved, not built7.8
Jaguar Land Rover Jaguar Plant, North Roadrooftop solar9.3approved, not built8.1
St Michaels Road, Ditton Roadbattery storage14approved, not built8.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.281, -2.797).