Solar, wind and battery projects near Ellesmere Port (CH66)
43 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of CH66 (Cheshire West and Chester): 5 are waiting for a planning decision, 26 approved but not yet running, 6 operational. The largest live scheme is Mollington (240 MW battery storage, approved on 7 May 2026, not yet built), 4.0 km away. Offshore, 3 wind farms are recorded within 40 km; the nearest is Burbo Bank (90 MW, operational), 28.6 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of CH66
Projects of 1 MW and more (21)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Capenhurst Lane, Capenhurstbattery storage | battery storage | 57 | under constructionupdated Sep 2022 | Jun 2021 | granted Mar 2022 | Sep 2022 | Cheshire West and Chester | 1.4 |
| Native Riverbattery storage | battery storage | 57 | operationalupdated Apr 2025 | Dec 2020 | granted Apr 2021 | Apr 2025 | Cheshire West and Chester | 1.5 |
| Capenhurst Lane, Capenhurstbattery storage | battery storage | 100 | approved, not builtupdated Dec 2023 | Sep 2022 | granted Dec 2023 | Dec 2023 | Cheshire West and Chester | 2.2 |
| Rectory Lanebattery storage | battery storage | 200 | approved, not builtupdated Jun 2025 | Aug 2024 | granted May 2025 | Jun 2025 | Cheshire West and Chester | 2.5 |
| National Grid Electricity Substation, Capenhurst Lanebattery storage | battery storage | 100 | operationalupdated Feb 2023 | Oct 2020 | granted Feb 2021 | Feb 2023 | Cheshire West and Chester | 2.5 |
| Cheshire Power Stationbattery storage | battery storage | 45 | approved, not built may be out of dateupdated Dec 2021 | Nov 2021 | granted May 2023 | Dec 2021 | Cheshire West and Chester | 2.8 |
| Jaguar Landrover Phoenix Building, Eric Foundation Roadrooftop solar | rooftop solar | 1.3 | approved, not builtupdated May 2025 | Feb 2025 | granted Apr 2025 | May 2025 | Cheshire West and Chester | 3.1 |
| Mollingtonbattery storage | battery storage | 240 | approved, not builtupdated Jun 2026 | Jan 2025 | granted May 2026 | Jun 2026 | Cheshire West and Chester | 4.0 |
| Eastham Balacing Services Plantbattery storage | battery storage | 27 | application withdrawnupdated Nov 2018 | Oct 2017 | — | Nov 2018 | Wirral | 4.5 |
| Oil Sites Roadbattery storage | battery storage | 9.6 | approved, not built may be out of dateupdated Apr 2020 | Aug 2017 | granted Oct 2017 | Apr 2020 | Cheshire West and Chester | 4.5 |
| Land West Of Vicarage Lanesolar farm | solar farm | 5 | application submitted may be out of dateupdated Jul 2015 | May 2015 | — | Jul 2015 | Cheshire West and Chester | 6.0 |
| Aldi Distribution Centre - Nestonrooftop solar | rooftop solar | 1.2 | operationalupdated Dec 2015 | Jul 2013 | granted Sep 2013 | Dec 2015 | Cheshire West and Chester | 6.4 |
| Wervin Road, Wervinsolar farm | solar farm | 3.5 | application submittedupdated May 2026 | Apr 2026 | — | May 2026 | Cheshire West and Chester | 6.4 |
| Shotwick Solar Farmsolar farm | solar farm | 72.2 | operationalupdated Feb 2018 | Feb 2014 | granted Jun 2015 | Feb 2018 | Flintshire | 7.0 |
| Toyota Motor Manufacturing Uk - Deesidesolar farm | solar farm | 3.8 | operationalupdated Nov 2014 | Oct 2013 | granted Dec 2013 | Nov 2014 | Flintshire | 8.0 |
| Banks Farm Solar Park (linked site)solar farm | solar farm | 5 | refused on appealupdated Dec 2016 | May 2015 | refused Apr 2016 | Dec 2016 | Flintshire | 8.7 |
| Wood Farm Solar Park (linked site)solar farm | solar farm | 5 | refused on appealupdated Dec 2016 | May 2015 | refused Apr 2016 | Dec 2016 | Flintshire | 8.8 |
| Land At Elton Farmsolar farm | solar farm | 5 | application submitted may be out of dateupdated Jul 2015 | May 2015 | — | Jul 2015 | Cheshire West and Chester | 9.3 |
| Hob Lane, Dunham On The Hill Solar Farmsolar farm | solar farm | 30 | application submittedupdated Jul 2025 | May 2025 | — | Jul 2025 | Cheshire West and Chester | 9.4 |
| Land off, Common Lanesolar farm | solar farm | 5 | refused on appealupdated May 2016 | Apr 2015 | refused Oct 2015 | May 2016 | Cheshire West and Chester | 9.4 |
| Liverpool John Lennon Airport Solar Farmsolar farm | solar farm | 3 | refusedupdated Jan 2022 | Dec 2021 | refused Jun 2022 | Jan 2022 | Liverpool | 9.7 |
Smaller schemes under 1 MW, mostly rooftop solar (22)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Urenco Uk Limited, Capenhurst Lanerooftop solar | rooftop solar | 0.2 | approved, not built may be out of dateupdated Jun 2023 | May 2023 | granted Jul 2023 | Jun 2023 | Cheshire West and Chester | 1.8 |
| Chester Gatesrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jan 2024 | Nov 2023 | granted Jan 2024 | Jan 2024 | Cheshire West and Chester | 3.4 |
| Ellesmere Port Sports Village Solar Arraysrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Dec 2021 | Sep 2021 | granted Oct 2021 | Dec 2021 | Cheshire West and Chester | 3.7 |
| Longlooms Road Eastrooftop solar | rooftop solar | 0.2 | operationalupdated Jun 2022 | Jun 2022 | granted Oct 2022 | Jun 2022 | Cheshire West and Chester | 4.0 |
| Sainsburys, Kinsey Roadrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Jul 2025 | May 2025 | granted Jul 2025 | Jul 2025 | Cheshire West and Chester | 4.2 |
| Iceland Foods, Second Avenuerooftop solar | rooftop solar | — | approved, not builtupdated Feb 2023 | Nov 2022 | granted Jan 2023 | Feb 2023 | Flintshire | 6.9 |
| Quay Pharmaceuticals Limited, Quay Houserooftop solar | rooftop solar | 0.2 | approved, not builtupdated Apr 2024 | Feb 2024 | granted Apr 2024 | Apr 2024 | Flintshire | 7.6 |
| The Countess Of Chester Health Park, Bowmere Hospitalrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Dec 2025 | Oct 2025 | granted Nov 2025 | Dec 2025 | Cheshire West and Chester | 7.8 |
| Garston Shore Roadrooftop solar | rooftop solar | 0.5 | approved, not built may be out of dateupdated Aug 2022 | Jun 2022 | granted Sep 2022 | Aug 2022 | Liverpool | 7.9 |
| Gowy Solar Parkrooftop solar | rooftop solar | — | application submittedupdated Jan 2026 | Nov 2025 | — | Jan 2026 | Cheshire West and Chester | 8.0 |
| Mill Lanerooftop solar | rooftop solar | 0.3 | approved, not builtupdated Mar 2022 | Feb 2022 | granted Apr 2022 | Mar 2022 | Cheshire West and Chester | 8.1 |
| Biffa Waste Services, Dock Road South Battery Storage Unitsbattery storage | battery storage | — | approved, not built may be out of dateupdated Jan 2023 | Nov 2022 | granted Dec 2022 | Jan 2023 | Wirral | 8.3 |
| Estuary Boulevardrooftop solar | rooftop solar | 0.6 | approved, not builtupdated Apr 2024 | Jan 2024 | granted Mar 2024 | Apr 2024 | Liverpool | 8.3 |
| Speke Hall Avenuebattery storage | battery storage | — | approved, not builtupdated Mar 2025 | Dec 2023 | granted Feb 2025 | Mar 2025 | Liverpool | 8.7 |
| Ash Road, Eltonbattery storage | battery storage | — | application withdrawnupdated Jun 2026 | Dec 2023 | — | Jun 2026 | Cheshire West and Chester | 9.0 |
| Inchcape Volkswagen Chester, Sealand Roadrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Sep 2023 | Jul 2023 | granted Aug 2023 | Sep 2023 | Cheshire West and Chester | 9.1 |
| Deeside Power Stationbattery storage | battery storage | — | approved, not builtupdated Jun 2022 | May 2022 | granted Aug 2022 | Jun 2022 | Flintshire | 9.2 |
| Big Storage Self Storage, Sealand Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Nov 2022 | Sep 2022 | granted Oct 2022 | Nov 2022 | Cheshire West and Chester | 9.2 |
| Hoole Roadrooftop solar | rooftop solar | — | approved, not builtupdated Jul 2026 | Mar 2026 | granted May 2026 | Jul 2026 | Cheshire West and Chester | 9.5 |
| Bumpers Lanerooftop solar | rooftop solar | 0.2 | approved, not builtupdated Oct 2024 | Sep 2024 | granted Oct 2024 | Oct 2024 | Cheshire West and Chester | 9.6 |
| Victoria Roadrooftop solar | rooftop solar | 0.1 | approved, not builtupdated Dec 2021 | Sep 2021 | granted Oct 2021 | Dec 2021 | Cheshire West and Chester | 9.6 |
| Self Storage Liverpool South, Goodlass Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jul 2025 | Apr 2025 | granted Jun 2025 | Jul 2025 | Liverpool | 9.6 |
Distance from the average position of the CH66 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 10 | 4 | 0 | 2 | 4 | 43.5 |
| Rooftop solar | 20 | 1 | 17 | 2 | 0 | 5.6 |
| Battery storage | 13 | 0 | 9 | 2 | 0 | 652 |
MW in pipeline: pending, approved and under-construction capacity.
Offshore wind farms within 40 km
| Wind farm | MW | Status (REPD) | km |
|---|---|---|---|
| Burbo Bank | 90 | operationalupdated Feb 2018 | 28.6 |
| Burbo Bank Extension (Burbo Bank 2) | 258 | operationalupdated May 2018 | 31.5 |
| North Hoyle | 60 | operationalupdated Aug 2017 | 37.3 |
Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.
How Cheshire West and Chester decides solar, wind and battery applications
| Applications | Cheshire West and Chester | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 54 | 10,236 |
| Refused | 6 (11%) | 19% |
| Solar refused | 3 of 40 | 12% |
| Onshore wind refused | 1 of 2 | 45% |
| Battery storage refused | 2 of 12 | 16% |
| Median time from submission to decision | 10.1 weeks | 17.0 weeks |
| Appeals lodged / allowed | 1 / 2 | — |
All projects in Cheshire West and Chester
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near CH66, 7 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.