Shotwick Solar Farm (72.2 MW)

Shotwick Solar Farm is a 72.2 MW solar farm project in Flintshire, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2016; the record was last updated on 2 February 2018.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

72.2 MWsolar farm
operationalstatus in REPD
2 February 2018record last updated
Flintshirecouncil area

Planning timeline

DateStage
21 February 2014Application submitted
1 June 2015Planning permission granted
15 November 2015Construction started
31 March 2016Operational

Project details

Technology
solar farm
Capacity
72.2 MW
Status (REPD)
operational
Record last updated
2 February 2018
Operator or applicant
Foresight Solar Fund
Planning authority
Flintshire
Planning application reference
51772
Address (REPD)
Weighbridge Road, Sealand, Deeside, Clwyd,
Council area (by location)
Flintshire
Time to decision
66 weeks
REPD reference
2347

Who decides

ApplicationsFlintshireUK
Decided applications (solar, wind, battery)1810,236
Refused4 (22%)19%
Solar refused2 of 1312%
Onshore wind refused2 of 345%
Battery storage refused0 of 216%
Median time from submission to decision30.3 weeks17.0 weeks
Appeals lodged / allowed2 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Land West Of Vicarage Lanesolar farm5application submitted1.4
Mollingtonbattery storage240approved, not built4.3
Rectory Lanebattery storage200approved, not built4.5
National Grid Electricity Substation, Capenhurst Lanebattery storage100operational4.9
Banks Farm Solar Park (linked site)solar farm5refused on appeal5.2
Capenhurst Lane, Capenhurstbattery storage57under construction5.7
Native Riverbattery storage57operational5.8
Capenhurst Lane, Capenhurstbattery storage100approved, not built6.0
Wood Farm Solar Park (linked site)solar farm5refused on appeal6.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.2409, -3.0227).