Capenhurst Lane, Capenhurst (57 MW battery storage)

Capenhurst Lane, Capenhurst is a 57 MW battery storage project in Cheshire West and Chester, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 1 September 2022; the record was last updated on 15 September 2022.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

57 MWbattery storage
under constructionstatus in REPD
15 September 2022record last updated
Cheshire West and Chestercouncil area

Planning timeline

DateStage
3 June 2021Application submitted
11 March 2022Planning permission granted
1 September 2022Construction started

Project details

Technology
battery storage (stand-alone storage)
Capacity
57 MW
Status (REPD)
under construction
Record last updated
15 September 2022
Operator or applicant
HD888CAP Limited
Planning authority
Cheshire West and Chester
Planning application reference
21/02404/FUL
Address (REPD)
Capenhurst Lane Capenhurst Chester
Council area (by location)
Cheshire West and Chester
Time to decision
40 weeks
Name in REPD
Capenhurst Lane, Capenhurst - Battery storage
REPD reference
9377

Who decides

ApplicationsCheshire West and ChesterUK
Decided applications (solar, wind, battery)5410,236
Refused6 (11%)19%
Solar refused3 of 4012%
Onshore wind refused1 of 245%
Battery storage refused2 of 1216%
Median time from submission to decision10.1 weeks17.0 weeks
Appeals lodged / allowed1 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Native Riverbattery storage57operational0.4
Rectory Lanebattery storage200approved, not built1.1
National Grid Electricity Substation, Capenhurst Lanebattery storage100operational1.2
Capenhurst Lane, Capenhurstbattery storage100approved, not built1.4
Mollingtonbattery storage240approved, not built2.7
Cheshire Power Stationbattery storage45approved, not built4.2
Land West Of Vicarage Lanesolar farm5application submitted4.6
Eastham Balacing Services Plantbattery storage27application withdrawn5.5
Oil Sites Roadbattery storage9.6approved, not built5.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.2679, -2.9503).