Energy Projects Near You

National Grid Electricity Substation, Capenhurst Lane (100 MW battery storage)

National Grid Electricity Substation, Capenhurst Lane is a 100 MW battery storage project in Cheshire West and Chester, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 11 February 2023; the record was last updated on 14 February 2023.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

100 MWbattery storage
operationalstatus in REPD
14 February 2023record last updated
Cheshire West and Chestercouncil area

Planning timeline

DateStage
7 October 2020Application submitted
1 February 2021Planning permission granted
11 February 2023Operational

Project details

Technology
battery storage (stand-alone storage)
Capacity
100 MW
Status (REPD)
operational
Record last updated
14 February 2023
Operator or applicant
Zenobe Energy Limited
Planning authority
Cheshire West and Chester
Planning application reference
20/03681/FUL
Address (REPD)
S/O National Grid Electricity Substation, Capenhurst Lane, Capenhurst, Chester
Council area (by location)
Cheshire West and Chester
Time to decision
17 weeks
Name in REPD
National Grid Electricity Substation, Capenhurst Lane - Battery Storage
REPD reference
12725

Who decides

ApplicationsCheshire West and ChesterUK
Decided applications (solar, wind, battery)5410,236
Refused6 (11%)19%
Solar refused3 of 4012%
Onshore wind refused1 of 245%
Battery storage refused2 of 1216%
Median time from submission to decision10.1 weeks17.0 weeks
Appeals lodged / allowed1 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Rectory Lanebattery storage200approved, not built1.0
Native Riverbattery storage57operational1.0
Capenhurst Lane, Capenhurstbattery storage100approved, not built1.1
Capenhurst Lane, Capenhurstbattery storage57under construction1.2
Mollingtonbattery storage240approved, not built1.5
Land West Of Vicarage Lanesolar farm5application submitted3.7
Shotwick Solar Farmsolar farm72.2operational4.9
Cheshire Power Stationbattery storage45approved, not built5.3
Oil Sites Roadbattery storage9.6approved, not built6.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.2569, -2.9534).