Energy Projects Near You

Capenhurst Lane, Capenhurst (100 MW battery storage)

Capenhurst Lane, Capenhurst is a 100 MW battery storage project in Cheshire West and Chester, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 8 December 2023, not yet built; the record was last updated on 13 December 2023.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

100 MWbattery storage
approved, not builtstatus in REPD
13 December 2023record last updated
Cheshire West and Chestercouncil area

Planning timeline

DateStage
22 September 2022Application submitted
8 December 2023Planning permission granted
8 December 2026Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
100 MW
Status (REPD)
approved, not built
Record last updated
13 December 2023
Operator or applicant
Aura Power BESS Limited
Planning authority
Cheshire West and Chester
Planning application reference
22/03585/FUL
Address (REPD)
South of Capenhurst Lane Capenhurst
Council area (by location)
Cheshire West and Chester
Time to decision
63 weeks
Name in REPD
Capenhurst Lane, Capenhurst - Battery Storage
REPD reference
12503

Who decides

ApplicationsCheshire West and ChesterUK
Decided applications (solar, wind, battery)5410,236
Refused6 (11%)19%
Solar refused3 of 4012%
Onshore wind refused1 of 245%
Battery storage refused2 of 1216%
Median time from submission to decision10.1 weeks17.0 weeks
Appeals lodged / allowed1 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Native Riverbattery storage57operational1.0
National Grid Electricity Substation, Capenhurst Lanebattery storage100operational1.1
Capenhurst Lane, Capenhurstbattery storage57under construction1.4
Rectory Lanebattery storage200approved, not built1.9
Mollingtonbattery storage240approved, not built2.0
Land West Of Vicarage Lanesolar farm5application submitted4.7
Cheshire Power Stationbattery storage45approved, not built4.8
Oil Sites Roadbattery storage9.6approved, not built5.2
Shotwick Solar Farmsolar farm72.2operational6.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.2574, -2.9376).