Mollington (240 MW battery storage)

Mollington is a 240 MW battery storage project in Cheshire West and Chester, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 7 May 2026, not yet built; the record was last updated on 15 June 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

240 MWbattery storage
approved, not builtstatus in REPD
15 June 2026record last updated
Cheshire West and Chestercouncil area

Planning timeline

DateStage
17 January 2025Application submitted
7 May 2026Planning permission granted
7 May 2029Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
240 MW
Status (REPD)
approved, not built
Record last updated
15 June 2026
Operator or applicant
Qair Renewables UK Limited
Planning authority
Cheshire West and Chester
Planning application reference
25/00132/FUL
Address (REPD)
S/O A494 Mollington, Chester
Council area (by location)
Cheshire West and Chester
Time to decision
68 weeks
Name in REPD
Mollington - Battery Energy Storage
REPD reference
18182

Who decides

ApplicationsCheshire West and ChesterUK
Decided applications (solar, wind, battery)5410,236
Refused6 (11%)19%
Solar refused3 of 4012%
Onshore wind refused1 of 245%
Battery storage refused2 of 1216%
Median time from submission to decision10.1 weeks17.0 weeks
Appeals lodged / allowed1 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
National Grid Electricity Substation, Capenhurst Lanebattery storage100operational1.5
Capenhurst Lane, Capenhurstbattery storage100approved, not built2.0
Rectory Lanebattery storage200approved, not built2.1
Native Riverbattery storage57operational2.5
Capenhurst Lane, Capenhurstbattery storage57under construction2.7
Land West Of Vicarage Lanesolar farm5application submitted2.9
Shotwick Solar Farmsolar farm72.2operational4.3
Banks Farm Solar Park (linked site)solar farm5refused on appeal4.7
Wood Farm Solar Park (linked site)solar farm5refused on appeal4.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.2442, -2.9589).