Wood Farm Solar Park (linked site) (5 MW)

Wood Farm Solar Park (linked site) is a 5 MW solar farm project in Flintshire, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 14 December 2016; the record was last updated on 23 December 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
refused on appealstatus in REPD
23 December 2016record last updated
Flintshirecouncil area

Planning timeline

DateStage
11 May 2015Application submitted
4 April 2016Refused by the planning authority
13 July 2016Appeal lodged
14 December 2016Appeal refused

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
refused on appeal
Record last updated
23 December 2016
Operator or applicant
SEP Solar
Planning authority
Flintshire
Planning application reference
53687
Appeal reference
APP/A6835/A/16/3151112
Site area
10.3 ha
Address (REPD)
Opp. Kingston Lane, Manor Farm, Deeside Lane, Sealand, Chester
Council area (by location)
Flintshire
Time to decision
47 weeks
REPD reference
5564

Who decides

ApplicationsFlintshireUK
Decided applications (solar, wind, battery)1810,236
Refused4 (22%)19%
Solar refused2 of 1312%
Onshore wind refused2 of 345%
Battery storage refused0 of 216%
Median time from submission to decision30.3 weeks17.0 weeks
Appeals lodged / allowed2 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Banks Farm Solar Park (linked site)solar farm5refused on appeal1.0
Bretton Hall Solar Farm (Wales)solar farm16approved, not built3.2
Bretton Hall Solar Farm (England)solar farm14approved, not built3.7
Mollingtonbattery storage240approved, not built4.9
Land West Of Vicarage Lanesolar farm5application submitted5.1
Shotwick Solar Farmsolar farm72.2operational6.1
National Grid Electricity Substation, Capenhurst Lanebattery storage100operational6.3
Capenhurst Lane, Capenhurstbattery storage100approved, not built6.6
Rectory Lanebattery storage200approved, not built6.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.2002, -2.9623).