Energy Projects Near You

Renewable energy projects in Flintshire

23 solar, wind or battery projects of 150 kW or more are located in Flintshire (REPD, July 2026 extract): 2 pending, 10 approved but not running, 5 operational and 4 refused. The council refused 4 of 18 decided applications (22%; UK 19%), with a median 30 weeks from submission to decision.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

23projects in the council area
2awaiting a decision
10approved, not running
22%of decisions refused

How Flintshire decides

ApplicationsFlintshireUK
Decided applications (solar, wind, battery)1810,236
Refused4 (22%)19%
Solar refused2 of 1312%
Onshore wind refused2 of 345%
Battery storage refused0 of 216%
Median time from submission to decision30.3 weeks17.0 weeks
Appeals lodged / allowed2 / 0—

Projects in Flintshire

Projects of 1 MW and more (15)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Tyn Y Coedbattery storagebattery storage500application submittedupdated Jul 2025May 2025—Jul 2025
Shotwick Solar Farmsolar farmsolar farm72.2operationalupdated Feb 2018Feb 2014granted Jun 2015Feb 2018
Bretton Hall Solar Farm (Wales)solar farmsolar farm16approved, not builtupdated Jan 2024Jul 2022granted Dec 2023Jan 2024
Bretton Hall Solar Farm (England)solar farmsolar farm14approved, not builtupdated Oct 2023May 2022granted Oct 2023Oct 2023
Kingspan Factory Wind Turbineswind farmwind farm5refusedupdated Jul 2014Dec 2011refused Nov 2013Jul 2014
Wood Farm Solar Park (linked site)solar farmsolar farm5refused on appealupdated Dec 2016May 2015refused Apr 2016Dec 2016
Banks Farm Solar Park (linked site)solar farmsolar farm5refused on appealupdated Dec 2016May 2015refused Apr 2016Dec 2016
Celyn Farmsolar farmsolar farm5abandonedupdated Oct 2017Oct 2015granted Aug 2016Oct 2017
Toyota Motor Manufacturing Uk - Deesidesolar farmsolar farm3.8operationalupdated Nov 2014Oct 2013granted Dec 2013Nov 2014
Flint Landfill Site Castle Parksolar farmsolar farm2operationalupdated Jul 2020Apr 2019granted Aug 2019Jul 2020
Kingspanwind farmwind farm1.8operationalupdated Jan 2019Nov 2014granted Apr 2015Jan 2019
Crumps Yard Solar Farmsolar farmsolar farm1.6operationalupdated Feb 2021Dec 2019granted Sep 2020Feb 2021
Lygan Uchaf Farm Wind Turbinewind turbinewind turbine1.3refusedupdated May 2015Jul 2014refused Apr 2015May 2015
British Aerospace Airbus, Chester Roadsolar farmsolar farm1.3approved, not builtupdated Dec 2025Jun 2025granted Sep 2025Dec 2025
The Bungalow, Kus Industrial Estaterooftop solarrooftop solar1.1approved, not builtupdated Dec 2022Oct 2022granted Dec 2022Dec 2022
Smaller schemes under 1 MW, mostly rooftop solar (8)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Llanasa Waste Treatment Workssolar farmsolar farm0.9application withdrawnupdated Sep 2019Jan 2019—Sep 2019
Staycold Export, Manor Lanerooftop solarrooftop solar0.9approved, not builtupdated Apr 2024Feb 2024granted Apr 2024Apr 2024
Als Laboratories Uk, Manor Roadrooftop solarrooftop solar0.5application submitted may be out of dateupdated Oct 2023Sep 2023—Oct 2023
Quay Pharmaceuticals Limited, Quay Houserooftop solarrooftop solar0.2approved, not builtupdated Apr 2024Feb 2024granted Apr 2024Apr 2024
Deeside Power Stationbattery storagebattery storage—approved, not builtupdated Jun 2022May 2022granted Aug 2022Jun 2022
Bretton Hall Solar Farm (Wales)battery storagebattery storage—approved, not built may be out of dateupdated Jul 2022Jul 2022granted Dec 2023Jul 2022
Bretton Hall Solar Farm (England)battery storagebattery storage—approved, not builtupdated Jan 2025May 2022granted Oct 2023Jan 2025
Iceland Foods, Second Avenuerooftop solarrooftop solar—approved, not builtupdated Feb 2023Nov 2022granted Jan 2023Feb 2023

Postcode districts in Flintshire

DistrictProjects within 10 kmPendingApprovedOperational
CH5343217
CH613236
CH710233
CH85002

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Projects belong to Flintshire by location (nearest postcode to the REPD grid reference); decisions are counted by the planning authority named in REPD.