Energy Projects Near You

Solar, wind and battery projects near Mold (CH7)

10 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of CH7 (Flintshire): 2 are waiting for a planning decision, 3 approved but not yet running, 3 operational. The largest live scheme is Tyn Y Coed (500 MW battery storage, application submitted on 30 May 2025, no decision recorded), 5.4 km away. Offshore, 3 wind farms are recorded within 40 km; the nearest is North Hoyle (60 MW, operational), 34.6 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10projects within 10 km
2awaiting a decision
3approved, not running
3operational

Projects within 10 km of CH7

Projects of 1 MW and more (7)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Celyn Farmsolar farmsolar farm5abandonedupdated Oct 2017Oct 2015granted Aug 2016Oct 2017Flintshire4.0
Tyn Y Coedbattery storagebattery storage500application submittedupdated Jul 2025May 2025—Jul 2025Flintshire5.4
Lygan Uchaf Farm Wind Turbinewind turbinewind turbine1.3refusedupdated May 2015Jul 2014refused Apr 2015May 2015Flintshire5.9
Crumps Yard Solar Farmsolar farmsolar farm1.6operationalupdated Feb 2021Dec 2019granted Sep 2020Feb 2021Flintshire7.6
The Bungalow, Kus Industrial Estaterooftop solarrooftop solar1.1approved, not builtupdated Dec 2022Oct 2022granted Dec 2022Dec 2022Flintshire9.0
Flint Landfill Site Castle Parksolar farmsolar farm2operationalupdated Jul 2020Apr 2019granted Aug 2019Jul 2020Flintshire9.6
Toyota Motor Manufacturing Uk - Deesidesolar farmsolar farm3.8operationalupdated Nov 2014Oct 2013granted Dec 2013Nov 2014Flintshire9.6
Smaller schemes under 1 MW, mostly rooftop solar (3)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Deeside Power Stationbattery storagebattery storage—approved, not builtupdated Jun 2022May 2022granted Aug 2022Jun 2022Flintshire8.7
Als Laboratories Uk, Manor Roadrooftop solarrooftop solar0.5application submitted may be out of dateupdated Oct 2023Sep 2023—Oct 2023Flintshire9.4
Staycold Export, Manor Lanerooftop solarrooftop solar0.9approved, not builtupdated Apr 2024Feb 2024granted Apr 2024Apr 2024Flintshire9.5

Distance from the average position of the CH7 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm400300
Rooftop solar312002.5
Wind turbine100010
Battery storage21100500

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
North Hoyle60operationalupdated Aug 201734.6
Burbo Bank90operationalupdated Feb 201835.5
Burbo Bank Extension (Burbo Bank 2)258operationalupdated May 201835.7

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How Flintshire decides solar, wind and battery applications

ApplicationsFlintshireUK
Decided applications (solar, wind, battery)1810,236
Refused4 (22%)19%
Solar refused2 of 1312%
Onshore wind refused2 of 345%
Battery storage refused0 of 216%
Median time from submission to decision30.3 weeks17.0 weeks
Appeals lodged / allowed2 / 0—

All projects in Flintshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near CH7, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.