Energy Projects Near You

Tyn Y Coed (500 MW battery storage)

Tyn Y Coed is a 500 MW battery storage project in Flintshire, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 30 May 2025, no decision recorded; the record was last updated on 22 July 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

500 MWbattery storage
application submittedstatus in REPD
22 July 2025record last updated
Flintshirecouncil area

Planning timeline

DateStage
30 May 2025Application submitted

Project details

Technology
battery storage (stand-alone storage)
Capacity
500 MW
Status (REPD)
application submitted
Record last updated
22 July 2025
Operator or applicant
NatPower UK
Planning authority
Flintshire
Planning application reference
FUL/000450/25
Address (REPD)
Adj To Tyn Y Coed, Starkey Lane, Northop, Mold
Council area (by location)
Flintshire
Name in REPD
Tyn Y Coed - Battery Energy Storage System
REPD reference
19130

Who decides

ApplicationsFlintshireUK
Decided applications (solar, wind, battery)1810,236
Refused4 (22%)19%
Solar refused2 of 1312%
Onshore wind refused2 of 345%
Battery storage refused0 of 216%
Median time from submission to decision30.3 weeks17.0 weeks
Appeals lodged / allowed2 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Shotwick Solar Farmsolar farm72.2operational6.9
Land West Of Vicarage Lanesolar farm5application submitted8.2
Celyn Farmsolar farm5abandoned9.1
Kingspan Factory Wind Turbineswind farm5refused9.4
Banks Farm Solar Park (linked site)solar farm5refused on appeal9.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.218, -3.1194).