Energy Projects Near You

Kingspan Factory Wind Turbines (5 MW)

Kingspan Factory Wind Turbines is a 5 MW wind farm project in Flintshire, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 7 November 2013; the record was last updated on 3 July 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWwind farm
refusedstatus in REPD
3 July 2014record last updated
Flintshirecouncil area

Planning timeline

DateStage
19 December 2011Application submitted
7 November 2013Refused by the planning authority

Project details

Technology
wind farm
Capacity
5 MW
Status (REPD)
refused
Record last updated
3 July 2014
Operator or applicant
Wind Direct
Planning authority
Flintshire
Planning application reference
49300
Turbines
2
Address (REPD)
Kingspan Limited, 2-4 Greenfield Business Park 2, Ba, Greenfield, Holywell, CH8 7GJ
Council area (by location)
Flintshire
Time to decision
98 weeks
REPD reference
4089

Who decides

ApplicationsFlintshireUK
Decided applications (solar, wind, battery)1810,236
Refused4 (22%)19%
Solar refused2 of 1312%
Onshore wind refused2 of 345%
Battery storage refused0 of 216%
Median time from submission to decision30.3 weeks17.0 weeks
Appeals lodged / allowed2 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Tyn Y Coedbattery storage500application submitted9.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.2889, -3.1973).