Kingspan Factory Wind Turbines (5 MW)
Kingspan Factory Wind Turbines is a 5 MW wind farm project in Flintshire, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 7 November 2013; the record was last updated on 3 July 2014.
5 MWwind farm
refusedstatus in REPD
3 July 2014record last updated
Flintshirecouncil area
Planning timeline
| Date | Stage |
|---|---|
| 19 December 2011 | Application submitted |
| 7 November 2013 | Refused by the planning authority |
Project details
- Technology
- wind farm
- Capacity
- 5 MW
- Status (REPD)
- refused
- Record last updated
- 3 July 2014
- Operator or applicant
- Wind Direct
- Planning authority
- Flintshire
- Planning application reference
- 49300
- Turbines
- 2
- Address (REPD)
- Kingspan Limited, 2-4 Greenfield Business Park 2, Ba, Greenfield, Holywell, CH8 7GJ
- Council area (by location)
- Flintshire
- Time to decision
- 98 weeks
- REPD reference
- 4089
Who decides
| Applications | Flintshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 18 | 10,236 |
| Refused | 4 (22%) | 19% |
| Solar refused | 2 of 13 | 12% |
| Onshore wind refused | 2 of 3 | 45% |
| Battery storage refused | 0 of 2 | 16% |
| Median time from submission to decision | 30.3 weeks | 17.0 weeks |
| Appeals lodged / allowed | 2 / 0 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Tyn Y Coed | battery storage | 500 | application submitted | 9.4 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.2889, -3.1973).