Energy Projects Near You

Solar, wind and battery projects near Holywell (CH8)

5 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of CH8 (Flintshire): 2 operational. The largest scheme is Kingspan Factory Wind Turbines (5 MW wind farm, refused on 7 November 2013), 3.3 km away. Offshore, 5 wind farms are recorded within 40 km; the nearest is North Hoyle (60 MW, operational), 20.1 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5projects within 10 km
0awaiting a decision
0approved, not running
2operational

Projects within 10 km of CH8

Projects of 1 MW and more (4)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Kingspanwind farmwind farm1.8operationalupdated Jan 2019Nov 2014granted Apr 2015Jan 2019Flintshire3.1
Kingspan Factory Wind Turbineswind farmwind farm5refusedupdated Jul 2014Dec 2011refused Nov 2013Jul 2014Flintshire3.3
Flint Landfill Site Castle Parksolar farmsolar farm2operationalupdated Jul 2020Apr 2019granted Aug 2019Jul 2020Flintshire7.7
Lygan Uchaf Farm Wind Turbinewind turbinewind turbine1.3refusedupdated May 2015Jul 2014refused Apr 2015May 2015Flintshire9.3
Smaller schemes under 1 MW, mostly rooftop solar (1)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Llanasa Waste Treatment Workssolar farmsolar farm0.9application withdrawnupdated Sep 2019Jan 2019—Sep 2019Flintshire8.5

Distance from the average position of the CH8 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm200100
Wind farm200110
Wind turbine100010

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
North Hoyle60operationalupdated Aug 201720.1
Burbo Bank Extension (Burbo Bank 2)258operationalupdated May 201822.0
Burbo Bank90operationalupdated Feb 201823.2
Rhyl Flats90operationalupdated Aug 201728.2
Gwynt y Mor576operationalupdated Aug 202031.6

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How Flintshire decides solar, wind and battery applications

ApplicationsFlintshireUK
Decided applications (solar, wind, battery)1810,236
Refused4 (22%)19%
Solar refused2 of 1312%
Onshore wind refused2 of 345%
Battery storage refused0 of 216%
Median time from submission to decision30.3 weeks17.0 weeks
Appeals lodged / allowed2 / 0—

All projects in Flintshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.