Solar, wind and battery projects near Prestatyn (LL19)
7 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of LL19 (Denbighshire): 2 are waiting for a planning decision, 1 approved but not yet running, 1 operational. The largest live scheme is Bodelwyddan, Abergele Road Solar Farm & Battery Storage (110 MW solar farm, application submitted on 20 May 2026, no decision recorded), 9.7 km away. Offshore, 6 wind farms are recorded within 40 km; the nearest is North Hoyle (60 MW, operational), 9.9 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of LL19
Projects of 1 MW and more (4)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Elwy Solar Energy Farmsolar farm | solar farm | 62 | refusedupdated Jul 2022 | Mar 2021 | refused Jul 2022 | Jul 2022 | Denbighshire | 8.0 |
| Kinmel 1 CICsolar farm | solar farm | 5 | operationalupdated Jul 2016 | Aug 2014 | granted Mar 2015 | Jul 2016 | Conwy | 9.1 |
| Bodelwyddan, Abergele Road Solar Farm & Battery Storagesolar farm | solar farm | 110 | application submittedupdated Jun 2026 | May 2026 | — | Jun 2026 | Denbighshire | 9.7 |
| Bodelwyddan, Abergele Road Solar Farm & Battery Storagebattery storage | battery storage | 110 | application submittedupdated Jun 2026 | May 2026 | — | Jun 2026 | Denbighshire | 9.7 |
Smaller schemes under 1 MW, mostly rooftop solar (3)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Llanasa Waste Treatment Workssolar farm | solar farm | 0.9 | application withdrawnupdated Sep 2019 | Jan 2019 | — | Sep 2019 | Flintshire | 6.3 |
| Elwy Solar Energy Farmbattery storage | battery storage | — | refusedupdated Jul 2022 | Mar 2021 | refused Jul 2022 | Jul 2022 | Denbighshire | 8.0 |
| Electricity Sub Station, Kinmel Park - Micro Energy Storage Facilitybattery storage | battery storage | 0.2 | approved, not builtupdated Nov 2024 | Jul 2024 | granted Oct 2024 | Nov 2024 | Denbighshire | 9.8 |
Distance from the average position of the LL19 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 4 | 1 | 0 | 1 | 1 | 110 |
| Battery storage | 3 | 1 | 1 | 0 | 1 | 110 |
MW in pipeline: pending, approved and under-construction capacity.
Offshore wind farms within 40 km
| Wind farm | MW | Status (REPD) | km |
|---|---|---|---|
| North Hoyle | 60 | operationalupdated Aug 2017 | 9.9 |
| Rhyl Flats | 90 | operationalupdated Aug 2017 | 16.1 |
| Burbo Bank Extension (Burbo Bank 2) | 258 | operationalupdated May 2018 | 19.0 |
| Gwynt y Mor | 576 | operationalupdated Aug 2020 | 19.8 |
| Burbo Bank | 90 | operationalupdated Feb 2018 | 23.0 |
| Awel y Mor Offshore Wind Farm | 775 | approved, not builtupdated Mar 2026 | 30.0 |
Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.
How Denbighshire decides solar, wind and battery applications
| Applications | Denbighshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 10 | 10,236 |
| Refused | 3 (30%) | 19% |
| Solar refused | 0 of 2 | 12% |
| Onshore wind refused | 3 of 7 | 45% |
| Battery storage refused | 0 of 1 | 16% |
| Median time from submission to decision | 39.3 weeks | 17.0 weeks |
| Appeals lodged / allowed | 2 / 2 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.