Awel y Mor offshore wind farm

Awel y Mor Offshore Wind Farm is a 775 MW offshore wind farm in Welsh waters. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 20 September 2023, not yet built; the record was last updated on 31 March 2026. Its REPD grid reference is 14 km from the nearest postcode on land (LL30 2XD, Conwy). As a nationally significant project, it was decided by the Secretary of State for Energy Security and Net Zero on a Development Consent Order after examination by the Planning Inspectorate (EN010112).

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

775 MWoffshore wind farm
approved, not builtstatus in REPD
31 March 2026record last updated
14 km from land (Conwy)REPD location

Consent timeline

DateStage
20 April 2022Application submitted
20 September 2023Development consent granted (Secretary of State)
20 September 2030Permission due to expire (unless work starts)

Project details

Technology
offshore wind farm
Capacity
775 MW
Status (REPD)
approved, not built
Record last updated
31 March 2026
Operator or applicant
RWE Renewables
Consenting authority (REPD)
The Planning Inspectorate - National Infrastructure
Application reference
EN010112
Nearest postcode on land
LL30 2XD (Conwy), 14.5 km from the REPD grid reference
Time to decision
74 weeks
Contracts for Difference
AR7
REPD reference
7699

Official project record at the Planning Inspectorate

Who decides

As a nationally significant project, it was decided by the Secretary of State for Energy Security and Net Zero on a Development Consent Order after examination by the Planning Inspectorate (EN010112). All Energy Secretary decisions on solar and wind farms.

Postcode districts within 40 km

Districtkm
Llandudno (LL30)16.4
Llandudno Junction (LL31)19.5
Colwyn Bay (LL28)20.0
Colwyn Bay (LL29)20.6
Penmaenmawr (LL34)22.9
Conwy (LL32)23.2
Abergele (LL22)25.8
Llanfairfechan (LL33)26.6
Rhyl (LL18)27.7
Beaumaris (LL58)28.3
Prestatyn (LL19)30.0
Moelfre (LL72)31.6

Straight-line distance from the centre of each postcode district to the REPD grid reference of the wind farm, which is a single point for the whole site.

Other offshore wind projects within 30 km

ProjectMWStatuskm
Gwynt y Mor576operational11.7
Rhyl Flats90operational14.5
Mona Offshore Wind Farm1,500approved, not built19.0
North Hoyle60operational24.0

All offshore wind farms in UK waters

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database can lag behind consent decisions. Location: REPD grid reference (53.4654, -3.8023).