Energy Projects Near You

Solar, wind and battery projects near Colwyn Bay (LL28)

4 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of LL28 (Conwy): none of them is pending, approved or operational. The largest scheme is Nant Bach (27.5 MW wind farm, abandoned), 9.7 km away. Offshore, 6 wind farms are recorded within 40 km; the nearest is Rhyl Flats (90 MW, operational), 12.9 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

4projects within 10 km
0awaiting a decision
0approved, not running
0operational

Projects within 10 km of LL28

Projects of 1 MW and more (3)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Mynydd Llanelian Wind Farmwind farmwind farm6.5refusedupdated Mar 2005Feb 2001refused Jun 2001Mar 2005Conwy4.1
Mynydd Glyn Lws Wind Farmwind farmwind farm3.6refusedupdated Dec 2014Mar 1995refused Nov 2000Dec 2014Conwy9.4
Nant Bachwind farmwind farm27.5abandonedupdated Aug 2015Jul 2008granted Mar 2009Aug 2015Conwy9.7
Smaller schemes under 1 MW, mostly rooftop solar (1)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Pen Y Bryn Farm, Pen Y Brynwind turbinewind turbine0.8refusedupdated Jan 2024Aug 2023refused Jan 2024Jan 2024Conwy7.2

Distance from the average position of the LL28 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Wind farm300020
Wind turbine100010

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
Rhyl Flats90operationalupdated Aug 201712.9
Awel y Mor Offshore Wind Farm775approved, not builtupdated Mar 202620.0
Gwynt y Mor576operationalupdated Aug 202020.6
North Hoyle60operationalupdated Aug 201725.3
Mona Offshore Wind Farm1,500approved, not builtupdated Mar 202638.9
Burbo Bank Extension (Burbo Bank 2)258operationalupdated May 201839.0

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How Conwy decides solar, wind and battery applications

ApplicationsConwyUK
Decided applications (solar, wind, battery)1210,236
Refused5 (42%)19%
Solar refused0 of 112%
Onshore wind refused5 of 1045%
Battery storage refused0 of 116%
Median time from submission to decision31.3 weeks17.0 weeks
Appeals lodged / allowed1 / 0—

All projects in Conwy

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.