Nant Bach (27.5 MW wind farm)

Nant Bach is a 27.5 MW wind farm project in Conwy, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: abandoned; the record was last updated on 18 August 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

27.5 MWwind farm
abandonedstatus in REPD
18 August 2015record last updated
Conwycouncil area

Planning timeline

DateStage
12 July 2008Application submitted
11 March 2009Planning permission granted
11 March 2012Permission expired

Project details

Technology
wind farm
Capacity
27.5 MW
Status (REPD)
abandoned
Record last updated
18 August 2015
Operator or applicant
Vattenfall
Planning authority
Conwy
Planning application reference
0/35170
Turbines
11
Address (REPD)
Mwdwl Eithin near Llanfihangel Glyn Myfyr, Conwy
Council area (by location)
Conwy
Time to decision
35 weeks
REPD reference
4064

Earlier applications for this site

ApplicationMWSubmittedOutcome
Nant Bach 0/323343012 September 2006refused 14 November 2007

Who decides

ApplicationsConwyUK
Decided applications (solar, wind, battery)1210,236
Refused5 (42%)19%
Solar refused0 of 112%
Onshore wind refused5 of 1045%
Battery storage refused0 of 116%
Median time from submission to decision31.3 weeks17.0 weeks
Appeals lodged / allowed1 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Dolgarrog Hydro Power Stationbattery storage5permission expired5.5
Mynydd Llanelian Wind Farmwind farm6.5refused6.3
Moel Maelogen A Phase 2wind farm11.7operational7.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.2006, -3.7605).