Mynydd Llanelian Wind Farm (6.5 MW)
Mynydd Llanelian Wind Farm is a 6.5 MW wind farm project in Conwy, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 15 June 2001; the record was last updated on 29 March 2005.
6.5 MWwind farm
refusedstatus in REPD
29 March 2005record last updated
Conwycouncil area
Planning timeline
| Date | Stage |
|---|---|
| 2 February 2001 | Application submitted |
| 15 June 2001 | Refused by the planning authority |
Project details
- Technology
- wind farm
- Capacity
- 6.5 MW
- Status (REPD)
- refused
- Record last updated
- 29 March 2005
- Operator or applicant
- WINDJEN POWER LTD
- Planning authority
- Conwy
- Planning application reference
- not recorded
- Address (REPD)
- 5 km South of Colwyn Bay, Conwy
- Council area (by location)
- Conwy
- Time to decision
- 19 weeks
- REPD reference
- 2573
Who decides
| Applications | Conwy | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 12 | 10,236 |
| Refused | 5 (42%) | 19% |
| Solar refused | 0 of 1 | 12% |
| Onshore wind refused | 5 of 10 | 45% |
| Battery storage refused | 0 of 1 | 16% |
| Median time from submission to decision | 31.3 weeks | 17.0 weeks |
| Appeals lodged / allowed | 1 / 0 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Nant Bach | wind farm | 27.5 | abandoned | 6.3 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.2549, -3.7327).