Energy Projects Near You

Solar, wind and battery projects near Llanrwst (LL26)

6 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of LL26 (Conwy): 2 operational. The largest scheme is Nant Bach (27.5 MW wind farm, abandoned), 7.0 km away. Offshore, 4 wind farms are recorded within 40 km; the nearest is Rhyl Flats (90 MW, operational), 28.2 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6projects within 10 km
0awaiting a decision
0approved, not running
2operational

Projects within 10 km of LL26

Projects of 1 MW and more (6)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Moel Maelogen A Phase 2wind farmwind farm11.7operationalupdated May 2017Jun 2003granted Nov 2004May 2017Conwy4.1
Moel Maelogen Awind farmwind farm2.6operationalupdated Mar 2010Aug 1999granted Dec 1999Mar 2010Conwy4.1
Dolgarrog Hydro Power Stationbattery storagebattery storage5permission expiredupdated Jun 2019Oct 2017granted Jan 2020Jun 2019Conwy6.9
Nant Bachwind farmwind farm27.5abandonedupdated Aug 2015Jul 2008granted Mar 2009Aug 2015Conwy7.0
Llys Dymper Wind Farmwind farmwind farm23appeal withdrawnupdated Dec 2015Feb 2012refused Apr 2014Dec 2015Conwy8.3
Moel Rhiwlug Wind Farmwind farmwind farm19.2application withdrawnupdated Mar 2003——Mar 2003Conwy9.9

Distance from the average position of the LL26 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Wind farm500200
Battery storage100000

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
Rhyl Flats90operationalupdated Aug 201728.2
Awel y Mor Offshore Wind Farm775approved, not builtupdated Mar 202636.3
Gwynt y Mor576operationalupdated Aug 202036.6
North Hoyle60operationalupdated Aug 201738.2

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How Conwy decides solar, wind and battery applications

ApplicationsConwyUK
Decided applications (solar, wind, battery)1210,236
Refused5 (42%)19%
Solar refused0 of 112%
Onshore wind refused5 of 1045%
Battery storage refused0 of 116%
Median time from submission to decision31.3 weeks17.0 weeks
Appeals lodged / allowed1 / 0—

All projects in Conwy

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.