Llys Dymper Wind Farm (23 MW)

Llys Dymper Wind Farm is a 23 MW wind farm project in Conwy, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: appeal withdrawn; the record was last updated on 9 December 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

23 MWwind farm
appeal withdrawnstatus in REPD
9 December 2015record last updated
Conwycouncil area

Planning timeline

DateStage
16 February 2012Application submitted
9 April 2014Refused by the planning authority
23 January 2015Appeal lodged
9 March 2015Appeal withdrawn

Project details

Technology
wind farm
Capacity
23 MW
Status (REPD)
appeal withdrawn
Record last updated
9 December 2015
Operator or applicant
Windpower Wales
Planning authority
Conwy
Planning application reference
0/38695
Appeal reference
APP/T6905/A/14/2228788
Turbines
10
Address (REPD)
Land at Llys Dymper, Gwytherin, Llanrwst, Conwy
Council area (by location)
Conwy
Time to decision
112 weeks
REPD reference
3848

Earlier applications for this site

ApplicationMWSubmittedOutcome
Llys Dymper 0/3772249.57 March 2011withdrawn 29 September 2011

Who decides

ApplicationsConwyUK
Decided applications (solar, wind, battery)1210,236
Refused5 (42%)19%
Solar refused0 of 112%
Onshore wind refused5 of 1045%
Battery storage refused0 of 116%
Median time from submission to decision31.3 weeks17.0 weeks
Appeals lodged / allowed1 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Llyn Alwen Wind Farmwind farm19.3application withdrawn3.0
Moel Rhiwlug Wind Farmwind farm19.2application withdrawn3.5
Moel Maelogen A Phase 2wind farm11.7operational4.5
Pant y Maenwind farm17.5approved, not built8.3
Gorsedd Brân Wind Framwind farm35refused on appeal9.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.1143, -3.6685).