Energy Projects Near You

Gorsedd Brân Wind Fram (35 MW)

Gorsedd Brân Wind Fram is a 35 MW wind farm project in Denbighshire, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 18 November 2009; the record was last updated on 3 May 2010.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

35 MWwind farm
refused on appealstatus in REPD
3 May 2010record last updated
Denbighshirecouncil area

Planning timeline

DateStage
31 May 2007Application submitted
12 February 2008Refused by the planning authority
18 November 2009Appeal refused

Project details

Technology
wind farm
Capacity
35 MW
Status (REPD)
refused on appeal
Record last updated
3 May 2010
Operator or applicant
Tegni Cymru Cyf
Planning authority
Denbighshire
Planning application reference
25/2007/0642
Turbines
13
Address (REPD)
Clocaenog forest, Denbighshire
Council area (by location)
Denbighshire
Time to decision
37 weeks
REPD reference
3052

Who decides

ApplicationsDenbighshireUK
Decided applications (solar, wind, battery)1010,236
Refused3 (30%)19%
Solar refused0 of 212%
Onshore wind refused3 of 745%
Battery storage refused0 of 116%
Median time from submission to decision39.3 weeks17.0 weeks
Appeals lodged / allowed2 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Pant y Maenwind farm17.5approved, not built1.7
Brenig Wind Farmwind farm37.6operational3.2
Tir Mostyn And Foel Goch Wind Farmwind farm21.3operational3.3
Clocaenog Forest Wind Farmwind farm96operational7.4
Llyn Alwen Wind Farmwind farm19.3application withdrawn8.1
Llys Dymper Wind Farmwind farm23appeal withdrawn9.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.1318, -3.5335).