Energy Projects Near You

Solar, wind and battery projects near Denbigh (LL16)

6 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of LL16 (Denbighshire): 2 operational. The largest scheme is Elwy Solar Energy Farm (62 MW solar farm, refused on 1 July 2022), 9.3 km away. Offshore, 6 wind farms are recorded within 40 km; the nearest is Rhyl Flats (90 MW, operational), 25.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6projects within 10 km
0awaiting a decision
0approved, not running
2operational

Projects within 10 km of LL16

Projects of 1 MW and more (4)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Tir Mostyn And Foel Goch Wind Farmwind farmwind farm21.3operationalupdated Aug 2012Sep 1999granted Dec 2002Aug 2012Denbighshire8.5
Gorsedd Brân Wind Framwind farmwind farm35refused on appealupdated May 2010May 2007refused Feb 2008May 2010Denbighshire9.0
Elwy Solar Energy Farmsolar farmsolar farm62refusedupdated Jul 2022Mar 2021refused Jul 2022Jul 2022Denbighshire9.3
Brenig Wind Farmwind farmwind farm37.6operationalupdated Nov 2018Jun 2015granted May 2016Nov 2018Denbighshire9.7
Smaller schemes under 1 MW, mostly rooftop solar (2)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Llannerch Water Treatment Workssolar farmsolar farm0.4application withdrawnupdated Apr 2019Oct 2018—Apr 2019Denbighshire5.5
Elwy Solar Energy Farmbattery storagebattery storage—refusedupdated Jul 2022Mar 2021refused Jul 2022Jul 2022Denbighshire9.3

Distance from the average position of the LL16 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm200010
Wind farm300210
Battery storage100010

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
Rhyl Flats90operationalupdated Aug 201725.5
North Hoyle60operationalupdated Aug 201725.8
Gwynt y Mor576operationalupdated Aug 202032.5
Burbo Bank Extension (Burbo Bank 2)258operationalupdated May 201834.5
Burbo Bank90operationalupdated Feb 201837.5
Awel y Mor Offshore Wind Farm775approved, not builtupdated Mar 202639.7

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How Denbighshire decides solar, wind and battery applications

ApplicationsDenbighshireUK
Decided applications (solar, wind, battery)1010,236
Refused3 (30%)19%
Solar refused0 of 212%
Onshore wind refused3 of 745%
Battery storage refused0 of 116%
Median time from submission to decision39.3 weeks17.0 weeks
Appeals lodged / allowed2 / 2—

All projects in Denbighshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.