Tir Mostyn And Foel Goch Wind Farm (21.3 MW)
Tir Mostyn And Foel Goch Wind Farm is a 21.3 MW wind farm project in Denbighshire, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 June 2005; the record was last updated on 16 August 2012.
21.3 MWwind farm
operationalstatus in REPD
16 August 2012record last updated
Denbighshirecouncil area
Planning timeline
| Date | Stage |
|---|---|
| 22 September 1999 | Application submitted |
| 19 December 2002 | Planning permission granted |
| 1 June 2005 | Operational |
Project details
- Technology
- wind farm
- Capacity
- 21.3 MW
- Status (REPD)
- operational
- Record last updated
- 16 August 2012
- Operator or applicant
- Munich Re (previously Windjen Power Ltd)
- Planning authority
- Denbighshire
- Planning application reference
- 25/710/99/PF
- Turbines
- 25
- Address (REPD)
- Nantglyn, Denbighshire
- Council area (by location)
- Denbighshire
- Time to decision
- 169 weeks
- REPD reference
- 4689
Who decides
| Applications | Denbighshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 10 | 10,236 |
| Refused | 3 (30%) | 19% |
| Solar refused | 0 of 2 | 12% |
| Onshore wind refused | 3 of 7 | 45% |
| Battery storage refused | 0 of 1 | 16% |
| Median time from submission to decision | 39.3 weeks | 17.0 weeks |
| Appeals lodged / allowed | 2 / 2 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Brenig Wind Farm | wind farm | 37.6 | operational | 1.2 |
| Gorsedd Brân Wind Fram | wind farm | 35 | refused on appeal | 3.3 |
| Pant y Maen | wind farm | 17.5 | approved, not built | 3.5 |
| Clocaenog Forest Wind Farm | wind farm | 96 | operational | 5.1 |
| Derwydd Bach Wind Farm | wind farm | 23 | abandoned | 9.4 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.117, -3.4911).