Energy Projects Near You

Clocaenog Forest Wind Farm (96 MW)

Clocaenog Forest Wind Farm is a 96 MW wind farm project in Conwy, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 October 2019; the record was last updated on 17 February 2022. As a nationally significant project, it was decided by the Secretary of State responsible for energy at the time on a Development Consent Order after examination by the Planning Inspectorate (EN010013).

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

96 MWwind farm
operationalstatus in REPD
17 February 2022record last updated
Conwycouncil area

Planning timeline

DateStage
23 April 2013Application submitted
12 September 2014Development consent granted (Secretary of State)
19 March 2018Construction started
1 October 2019Operational

Project details

Technology
wind farm
Capacity
96 MW
Status (REPD)
operational
Record last updated
17 February 2022
Operator or applicant
RWE Innogy UK
Planning authority
The Planning Inspectorate - National Infrastructure
Planning application reference
EN010013
Turbines
32
Turbine height
145 m
Address (REPD)
Clocaenog forest, Ruthin,
Council area (by location)
Conwy
Time to decision
72 weeks
Contracts for Difference
AR1
REPD reference
4552

Official project record at the Planning Inspectorate (EN010013)

Who decides

As a nationally significant project, it was decided by the Secretary of State responsible for energy at the time on a Development Consent Order after examination by the Planning Inspectorate (EN010013). All Energy Secretary decisions on solar and wind farms. The Planning Inspectorate - National Infrastructure refused 7% of 46 decided solar, wind and battery applications in REPD (median 73 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Brenig Wind Farmwind farm37.6operational4.3
Derwydd Bach Wind Farmwind farm23abandoned4.7
Tir Mostyn And Foel Goch Wind Farmwind farm21.3operational5.1
Pant y Maenwind farm17.5approved, not built6.3
Gorsedd Brân Wind Framwind farm35refused on appeal7.4
Wern Ddu Wind Farmwind farm9.2operational7.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.071, -3.4892).