Energy Projects Near You

Wern Ddu Wind Farm (9.2 MW)

Wern Ddu Wind Farm is a 9.2 MW wind farm project in Denbighshire, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 March 2010; the record was last updated on 26 April 2010.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

9.2 MWwind farm
operationalstatus in REPD
26 April 2010record last updated
Denbighshirecouncil area

Planning timeline

DateStage
23 April 2004Application submitted
26 January 2005Planning permission granted
1 November 2009Construction started
1 March 2010Operational

Project details

Technology
wind farm
Capacity
9.2 MW
Status (REPD)
operational
Record last updated
26 April 2010
Operator or applicant
Tegni
Planning authority
Denbighshire
Planning application reference
6/2004/278/PS
Turbines
4
Address (REPD)
NW Corwen, Gwyddelwern, Corwen, Denbighshire
Council area (by location)
Denbighshire
Time to decision
40 weeks
REPD reference
3592

Who decides

ApplicationsDenbighshireUK
Decided applications (solar, wind, battery)1010,236
Refused3 (30%)19%
Solar refused0 of 212%
Onshore wind refused3 of 745%
Battery storage refused0 of 116%
Median time from submission to decision39.3 weeks17.0 weeks
Appeals lodged / allowed2 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Derwydd Bach Wind Farmwind farm23abandoned3.1
Clocaenog Forest Wind Farmwind farm96operational7.5
Gaerwen Wind Farmwind farm59.4application submitted9.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.0255, -3.4059).