Derwydd Bach Wind Farm (23 MW)
Derwydd Bach Wind Farm is a 23 MW wind farm project in Denbighshire, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: abandoned; the record was last updated on 17 December 2015.
23 MWwind farm
abandonedstatus in REPD
17 December 2015record last updated
Denbighshirecouncil area
Planning timeline
| Date | Stage |
|---|---|
| 20 July 2007 | Application submitted |
| 21 July 2011 | Planning permission granted |
Project details
- Technology
- wind farm
- Capacity
- 23 MW
- Status (REPD)
- abandoned
- Record last updated
- 17 December 2015
- Operator or applicant
- AGR Renewables
- Planning authority
- Denbighshire
- Planning application reference
- 04/2007/0964
- Turbines
- 10
- Address (REPD)
- Melin-Y-Wig, Corwe, Denbighshire
- Council area (by location)
- Denbighshire
- Time to decision
- 209 weeks
- REPD reference
- 3975
Who decides
| Applications | Denbighshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 10 | 10,236 |
| Refused | 3 (30%) | 19% |
| Solar refused | 0 of 2 | 12% |
| Onshore wind refused | 3 of 7 | 45% |
| Battery storage refused | 0 of 1 | 16% |
| Median time from submission to decision | 39.3 weeks | 17.0 weeks |
| Appeals lodged / allowed | 2 / 2 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Wern Ddu Wind Farm | wind farm | 9.2 | operational | 3.1 |
| Clocaenog Forest Wind Farm | wind farm | 96 | operational | 4.7 |
| Brenig Wind Farm | wind farm | 37.6 | operational | 8.9 |
| Tir Mostyn And Foel Goch Wind Farm | wind farm | 21.3 | operational | 9.4 |
| Gaerwen Wind Farm | wind farm | 59.4 | application submitted | 9.5 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.0362, -3.4481).