Energy Projects Near You

Solar, wind and battery projects near Ruthin (LL15)

No solar, wind or battery project of 150 kW or more is recorded within 10 km of the centre of LL15 (Ruthin) in the Renewable Energy Planning Database (July 2026 extract). The nearest is Wern Ddu Wind Farm (9.2 MW wind farm, operational), 10.5 km away. Offshore, 2 wind farms are recorded within 40 km; the nearest is North Hoyle (60 MW, operational), 36.0 km away.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10.5 kmto the nearest project
0projects within 10 km
0awaiting a decision
0approved, not running
0operational

The nearest recorded project is Wern Ddu Wind Farm, 10.5 km from the centre of LL15. Household rooftop panels and schemes below about 150 kW are not in the database.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
North Hoyle60operationalupdated Aug 201736.0
Rhyl Flats90operationalupdated Aug 201737.4

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How Denbighshire decides solar, wind and battery applications

ApplicationsDenbighshireUK
Decided applications (solar, wind, battery)1010,236
Refused3 (30%)19%
Solar refused0 of 212%
Onshore wind refused3 of 745%
Battery storage refused0 of 116%
Median time from submission to decision39.3 weeks17.0 weeks
Appeals lodged / allowed2 / 2—

All projects in Denbighshire