Energy Projects Near You

Solar, wind and battery projects near St Asaph (LL17)

7 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of LL17 (Denbighshire): 2 are waiting for a planning decision, 1 approved but not yet running, 1 operational. The largest live scheme is Bodelwyddan, Abergele Road Solar Farm & Battery Storage (110 MW solar farm, application submitted on 20 May 2026, no decision recorded), 5.4 km away. Offshore, 6 wind farms are recorded within 40 km; the nearest is North Hoyle (60 MW, operational), 18.4 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7projects within 10 km
2awaiting a decision
1approved, not running
1operational

Projects within 10 km of LL17

Projects of 1 MW and more (4)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Elwy Solar Energy Farmsolar farmsolar farm62refusedupdated Jul 2022Mar 2021refused Jul 2022Jul 2022Denbighshire2.3
Bodelwyddan, Abergele Road Solar Farm & Battery Storagesolar farmsolar farm110application submittedupdated Jun 2026May 2026—Jun 2026Denbighshire5.4
Bodelwyddan, Abergele Road Solar Farm & Battery Storagebattery storagebattery storage110application submittedupdated Jun 2026May 2026—Jun 2026Denbighshire5.4
Kinmel 1 CICsolar farmsolar farm5operationalupdated Jul 2016Aug 2014granted Mar 2015Jul 2016Conwy7.0
Smaller schemes under 1 MW, mostly rooftop solar (3)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Elwy Solar Energy Farmbattery storagebattery storage—refusedupdated Jul 2022Mar 2021refused Jul 2022Jul 2022Denbighshire2.3
Llannerch Water Treatment Workssolar farmsolar farm0.4application withdrawnupdated Apr 2019Oct 2018—Apr 2019Denbighshire2.9
Electricity Sub Station, Kinmel Park - Micro Energy Storage Facilitybattery storagebattery storage0.2approved, not builtupdated Nov 2024Jul 2024granted Oct 2024Nov 2024Denbighshire4.8

Distance from the average position of the LL17 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm41011110
Battery storage31101110

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
North Hoyle60operationalupdated Aug 201718.4
Rhyl Flats90operationalupdated Aug 201719.4
Gwynt y Mor576operationalupdated Aug 202025.7
Burbo Bank Extension (Burbo Bank 2)258operationalupdated May 201827.6
Burbo Bank90operationalupdated Feb 201831.1
Awel y Mor Offshore Wind Farm775approved, not builtupdated Mar 202633.9

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How Denbighshire decides solar, wind and battery applications

ApplicationsDenbighshireUK
Decided applications (solar, wind, battery)1010,236
Refused3 (30%)19%
Solar refused0 of 212%
Onshore wind refused3 of 745%
Battery storage refused0 of 116%
Median time from submission to decision39.3 weeks17.0 weeks
Appeals lodged / allowed2 / 2—

All projects in Denbighshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.