Moel Maelogen A Phase 2 (11.7 MW wind farm)

Moel Maelogen A Phase 2 is an 11.7 MW wind farm project in Conwy, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 October 2008; the record was last updated on 3 May 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

11.7 MWwind farm
operationalstatus in REPD
3 May 2017record last updated
Conwycouncil area

Planning timeline

DateStage
12 June 2003Application submitted
26 November 2004Planning permission granted
1 October 2008Operational

Project details

Technology
wind farm
Capacity
11.7 MW
Status (REPD)
operational
Record last updated
3 May 2017
Operator or applicant
John Laing Environmental Assets Group
Planning authority
Conwy
Planning application reference
0/27445
Turbines
9 (Welsh Government; REPD: 8)
Address (REPD)
Moel Maelogen, Nr Llanrwst, Conwy, Gwynedd
Council area (by location)
Conwy
Time to decision
76 weeks
REPD reference
3172

Who decides

ApplicationsConwyUK
Decided applications (solar, wind, battery)1210,236
Refused5 (42%)19%
Solar refused0 of 112%
Onshore wind refused5 of 1045%
Battery storage refused0 of 116%
Median time from submission to decision31.3 weeks17.0 weeks
Appeals lodged / allowed1 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Llys Dymper Wind Farmwind farm23appeal withdrawn4.5
Moel Rhiwlug Wind Farmwind farm19.2application withdrawn6.9
Llyn Alwen Wind Farmwind farm19.3application withdrawn7.4
Nant Bachwind farm27.5abandoned7.5
Dolgarrog Hydro Power Stationbattery storage5permission expired10.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.1363, -3.725).