Moel Maelogen A Phase 2 (11.7 MW wind farm)
Moel Maelogen A Phase 2 is an 11.7 MW wind farm project in Conwy, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 October 2008; the record was last updated on 3 May 2017.
11.7 MWwind farm
operationalstatus in REPD
3 May 2017record last updated
Conwycouncil area
Planning timeline
| Date | Stage |
|---|---|
| 12 June 2003 | Application submitted |
| 26 November 2004 | Planning permission granted |
| 1 October 2008 | Operational |
Project details
- Technology
- wind farm
- Capacity
- 11.7 MW
- Status (REPD)
- operational
- Record last updated
- 3 May 2017
- Operator or applicant
- John Laing Environmental Assets Group
- Planning authority
- Conwy
- Planning application reference
- 0/27445
- Turbines
- 9 (Welsh Government; REPD: 8)
- Address (REPD)
- Moel Maelogen, Nr Llanrwst, Conwy, Gwynedd
- Council area (by location)
- Conwy
- Time to decision
- 76 weeks
- REPD reference
- 3172
Who decides
| Applications | Conwy | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 12 | 10,236 |
| Refused | 5 (42%) | 19% |
| Solar refused | 0 of 1 | 12% |
| Onshore wind refused | 5 of 10 | 45% |
| Battery storage refused | 0 of 1 | 16% |
| Median time from submission to decision | 31.3 weeks | 17.0 weeks |
| Appeals lodged / allowed | 1 / 0 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Llys Dymper Wind Farm | wind farm | 23 | appeal withdrawn | 4.5 |
| Moel Rhiwlug Wind Farm | wind farm | 19.2 | application withdrawn | 6.9 |
| Llyn Alwen Wind Farm | wind farm | 19.3 | application withdrawn | 7.4 |
| Nant Bach | wind farm | 27.5 | abandoned | 7.5 |
| Dolgarrog Hydro Power Station | battery storage | 5 | permission expired | 10.0 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.1363, -3.725).